KDM Reveals Consultant Negligence in Jatiluhur AI Data Centre Project
West Java Governor Dedi Mulyadi has asserted that the temporary suspension of the Rp3.5 trillion artificial intelligence (AI) based data centre construction project in the Jatiluhur area is purely due to negligence by the consultants, who have been slow in submitting licensing data. This firm statement was made by Dedi to clarify the controversy surrounding the halt of the BDX Data Centres project and to refute allegations of bureaucratic hurdles within the Purwakarta Regency Government or the West Java Provincial Government.
“When I asked yesterday, the Building Permit (IMB) had not been issued. Has the Environmental Impact Assessment (Amdal) been released? Not yet. So, I said do not proceed with construction yet. The permits are not out. Where is the fault? With the Purwakata Local Government? No. The fault lies with the consultants, who had not even submitted the data by the time I arrived,” said Dedi Mulyadi in Bandung on Friday (2/10/2026).
KDM emphasised that the suspension, initiated following his sudden visit on Monday (28/9/2026), is a manifestation of his consistency in enforcing regulations to protect ecological interests and the rights of local residents to clean water supplies.
To ensure the objectivity of the policy, the West Java Provincial Government has involved academics from the University of Indonesia (UI) to provide independent studies and input regarding the environmental impact feasibility of the AI data centre project.
“Personally, if objectively the Amdal passes, I have no problem with it proceeding. If the Amdal says it is not permitted, I also have no problem with it being halted. But one note: the residents of Purwakarta, who sacrifice for the interests of Jatiluhur, must have access to water. It must not be disrupted,” he added.
Source: jawawa.id (https://jawawa.id/newsitem/kdm-reveals-consultant-negligence-in-jatiluhur-ai-data-centre-project-1790995997)
Originally published by Republika (https://news.republika.co.id/berita/tmb4ok409/kdm-ungkap-ada-kelalaian-konsultan-proyek-data-center-ai-jatiluhur), translated from Indonesian