The redevelopment of the Kampung Bahari area in Tanjung Priok, North Jakarta, is continuing. Following enforcement action by the police and the North Jakarta municipal administration, work has moved on to clearing unauthorised structures and debris around the railway line.
From Monday (2 November) to Friday (6 November), 58 wagons of material collected during trackside clearance were transported to Tanjung Priok Station. The clean-up is intended to safeguard rail services.
The operation involves KAI’s Jakarta Division 1, the police, the Indonesian Military (TNI), the North Jakarta municipal administration, the Public Order Agency (Satpol PP), public infrastructure and facilities handling officers (PPSU), and other relevant parties. The clean-up is focused on structures whose occupants have left, as well as material along both sides of the railway tracks.
KAI Jakarta Division 1 Public Relations Manager Franoto Wibowo said the work followed the area’s clearance operation and was being carried out through cooperation between agencies to support the safety of rail services and the public.
“After the police and local government carried out the clearance, we continued the area’s reorganisation through a joint trackside clean-up. Priority is being given to buildings that are no longer occupied and to material near the railway line that could pose a risk to the safety of train operations,” Franoto said on Friday (6 November 2026).
Preliminary data show that KAI’s asset area in Kampung Bahari covers approximately 47,537 square metres (4.7 hectares). The clean-up is being conducted in stages, taking account of conditions on the ground and the requirements for work in the railway area.
The material was transported in stages: five wagons on Monday (2 November), 20 on Tuesday (4 November), 24 on Wednesday (5 November), and nine on Thursday (6 November). The material was carried by train to the Tanjung Priok Station yard, then transferred to lorries provided by the North Jakarta municipal administration to be taken out of the station area.
Reorganisation of areas A1 to A11 in Kampung Bahari, also known as Kampung Muara Bahari, in Tanjung Priok sub-district, will continue until completion. The trackside clean-up will proceed in stages, with priority given to the safety of workers, uninterrupted train services and a humane approach to the surrounding community.
“Co-operation among all parties is an important part of reorganising Kampung Bahari. As the trackside clean-up continues, we hope the environment around the railway line will become more orderly and safer, helping protect both train operations and the public,” Franoto said.