KAI Reshapes the Karet–Sudirman Baru Area as Steel Structures Go Up

| Source: Antara (Indonesian) Translated from Indonesian | Infrastructure
KAI Reshapes the Karet–Sudirman Baru Area as Steel Structures Go Up
Image: Antara (Indonesian)

Jakarta (ANTARA) — The transfer of KRL services from Karet Station to Sudirman Baru Station on 1 September 2026 is part of a reorganisation of journeys in the area. Alongside the change, KAI is continuing to reorganise facilities and access around Karet and Sudirman Baru to improve passenger movement and connections to onward transport.

The latest progress shows that several sections of the lower structure have been completed, while steel structures have been installed in a number of areas. The work forms part of the area’s reorganisation and the provision of supporting facilities for passengers following the service transfer.

KAI data show that passenger activity in the area remains a key consideration in planning access. Karet Station recorded 4,909,334 entries and exits through its gates from January to August 2026, before the service transfer. Sudirman Baru Station recorded 2,439,757 entries and exits through its gates from January to September 2026. The figures cover different periods, reflecting the change in services, and therefore are not used to compare growth at the two stations.

In September 2026 alone, KRL gate entries and exits at Sudirman Baru reached 646,411, up from 190,060 in August. The change coincided with the transfer of services from Karet, which meant passenger activity was recorded at a different service location.

KAI Vice President of Corporate Communications Anne Purba said: “Changes in travel patterns need to be accompanied by improved access. We want passengers to be able to move around the Karet and Sudirman Baru areas more easily.”

The planned facilities include one 20-metre flat travelator and two vertical travelators. The area works also include a pedestrian corridor, landscaping, a drop-off area for onward transport, access escalators and a covered walkway. The project is scheduled to continue until 31 December 2026.

Anne said: “We are overseeing the work in stages, taking account of passengers’ needs and the conditions in the area. The facilities’ readiness will be confirmed before they are brought into use.”

KAI continues to monitor progress and adjust access arrangements to meet travel needs in the area. The company hopes the improved facilities and layout will provide passengers with better-organised access to onward public transport.

More from 24 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/kai-reshapes-the-karet-sudirman-baru-area-as-steel-structures-go-up-1792853560)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5809815/kai-tata-kawasan-karet-sudirman-baru-struktur-baja-mulai-terpasang), translated from Indonesian
Print