KAI Chief Tells Parliament That New KRL Orders From INKA Delayed By Over a Year

| Source: CNBC Indonesia Translated from Indonesian | Infrastructure
KAI Chief Tells Parliament That New KRL Orders From INKA Delayed By Over a Year
Image: CNBC Indonesia

The President Director of PT Kereta Api Indonesia (Persero), Bobby Rasyidin, has revealed that the order for 16 iE305/CLI-225 commuter train (KRL) sets from PT Industri Kereta Api (Persero), known as INKA, is behind schedule. Out of the 16 sets ordered, only seven have arrived and entered operation.

“The issue currently is that while 11 CRRC units have been operational since last year, only 7 of the 16 units from INKA are operational. We have yet to receive 9 units, resulting in a delay of more than a year,” Bobby stated during a working meeting with Commission VI of the House of Representatives (DPR) on Wednesday (23/09/2026).

Bobby explained that one of the primary issues is production capacity. According to Bobby, INKA’s production capacity has proven insufficient compared to their initial projections.

“Regarding the production capacity issue, PT INKA projected a capacity of 8 units per year for these 16 units. In reality, they are only producing 2 to 3 units per year,” he said.

Furthermore, Bobby mentioned that KAI has issued a recall for seven of the INKA KRL train sets.

“Three weeks ago, we recalled 7 INKA trainset units,” said Bobby.

Bobby explained that KAI identified issues after conducting inspections. He noted that certain components had the potential to disrupt the operations of the iE305/CLI-225 type KRL.

“We decided to recall them,” he stated.

Bobby noted that the inspections were carried out in involvement with INKA. A thorough check was performed on all seven INKA iE305/CLI-225 sets. Currently, one trainset has returned to operation, and another trainset has completed its inspection process today.

“We conducted a re-inspection involving INKA. There is one component that needs to be upgraded. We have already found a solution. One trainset has returned to operation, and another trainset completed its maintenance today,” he added.

More from 23 September 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/kai-chief-tells-parliament-that-new-krl-orders-from-inka-delayed-by-over-a-year-1790157383)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20260923153653-4-770285/bos-kai-curhat-ke-dpr-pesanan-krl-baru-dari-inka-molor-setahun-lebih), translated from Indonesian
Print