Jogja-Solo Toll Road Section 2.2 Reaches 86 Percent Completion, Targeted for September 2026

| Source: Antara (Indonesian) Translated from Indonesian | Infrastructure
Jogja-Solo Toll Road Section 2.2 Reaches 86 Percent Completion, Targeted for September 2026
Image: Antara (Indonesian)

Sleman (ANTARA) - PT Adhi Karya (Persero), the executing contractor, has recorded that construction of the Jogja-Solo Toll Road Section 2, Package 2.2, the Trihanggo-Junction segment in Sleman Regency, Special Region of Yogyakarta, has reached approximately 86 per cent and is targeted for completion through a “provisional hand over” (PHO) in September 2026.

Agung Murhandjanto, communications officer for PT Adhi Karya on the Jogja-Solo Toll Road Section 2, Package 2.2 project, said in Sleman on Thursday that the project has now entered the final stage of structural works after successfully carrying out girder erection for the access ramps (ramp on and ramp off).

“Insya Allah, as of now we have reached around 86 per cent. Last night we carried out the girder erection for the spanning beams, and for the ramp on and ramp off, alhamdulillah, these are now complete,” Agung said.

Agung said the next phase of work will focus on rebar installation, concrete road slab casting (rigid pavement), and asphalt laying in the ramp on and ramp off areas. In addition, the company is also finishing a toll gate featuring ornaments inspired by local culture.

In terms of connectivity, this toll road segment will later be physically connected directly to the Jogja-Bawen toll road. Traffic from both toll roads will be linked, with vehicles entering and exiting through the Trihanggo toll exit.

Responding to the challenge of constructing above a national traffic route with heavy mobility, Agung stressed that the contractor is applying strict occupational safety standard operating procedures (SOPs) to avoid the risk of accidents.

Among the mitigation measures implemented are requiring workers to wear complete personal protective equipment, installing safety nets on both sides of the elevated structure, and limiting working hours for heavy work such as concrete casting, which is carried out in the afternoon or at night when traffic volume decreases.

More from 23 July 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/jogja-solo-toll-road-section-2-2-reaches-86-percent-completion-targeted-for-september-2026-1784797064)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5662463/progres-jalan-tol-jogja-solo-capai-86-persen), translated from Indonesian
Print