The $410 million electricity project by state electricity company Perusahaan Listrik Negara to build a 220-kilometer overhead electricity transmission cable from Java to Bali is expected to be completed in 2019, a senior government official said on Monday.
Robert Pakpahan, director general of the Debt Management Office in the Finance Ministry, said the project, which involves carrying the cable over the sea via “towers as high as the Eiffel,” will also receive soft loans from the Asian Development Bank (ADB) and the Asean Infrastructure Fund (AIF).
The project to build a transmission cable capable of transmitting 1,500 megawatts of electricity through extra-high-voltage lines (500 Kilovolt), will receive $224 million from the ADB and $25 million from the AIF. The remaining financing will come from the government through PLN.
Robert said PLN will enjoy a breather during the development of the project, with construction scheduled to be completed in five years, while the first installment of the 20-year loan will only be due in the sixth year.
Robert said the interest charges will be equivalent to the Libor rate plus four basis points per year.
“This project is highly needed,” said Robert, whose office deals with the government’s loans from multilateral agencies such as ADB.
Bali is currently supplied by two undersea cables from Java with a total capacity of 200 mW, but it is not enough, causing frequent power outages on the island, reliant on tourism.
A more reliable electricity supply should allow faster growth in the industrial and commercial sectors, particularly in tourism, which, in turn, creates more jobs.
According to the ADB, the electrification ratio in Bali is 69 percent, with the commercial sector making up about 46 percent of total energy consumption on the island.
PLN has to resort to diesel-driven power generation to back up supply in Bali.
The company’s new cable is expected to create a more reliable supply to Bali and reduce electricity disruptions and diesel consumption.
The Malaysia-based AIF, established in 2011 by the 10 Asean members and the ADB, is expected to annually finance up to $300 million in infrastructure projects, including roads and railways, to be selected based on economic rates of return and impact on poverty reduction.
Asean consists of nine Southeast Asian countries, including Indonesia.
Source: jawawa.id (https://jawawa.id/newsitem/java-bali-power-cable-to-be-completed-in-2019-1388595600)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/business/java-bali-power-cable-to-be-completed-in-2019/)