Jasamarga to Repair Jakarta-Tangerang Toll Road until 23 April
PT Jasamarga Metropolitan Tollroad and PT Jasamarga Tollroad Maintenance are carrying out maintenance on the Jakarta-Tangerang Toll Road. Jasamarga Metropolitan, as the operator of the Jakarta-Tangerang Toll Road section, is performing scrapping, filling, overlay (SFO), and reconstruction of pavement works. Meanwhile, Jasamarga Tollroad Maintenance serves as the service provider in the field of toll road maintenance.
The road quality improvement and driving comfort enhancement project is intended to support the fulfilment of Minimum Service Standards (SPM) for toll roads. The SFO and pavement reconstruction works will take place over approximately two weeks, from Tuesday, 7 April to Thursday, 23 April 2026.
Ginanjar Bekti R., Senior Manager of Representative Office 2 at Jasamarga Metropolitan Tollroad, stated that the lanes subject to work will be temporarily impassable during the maintenance period. However, other lanes can be used for traffic.
“Jasamarga apologises for any inconvenience arising from these works,” said Ginanjar in a written statement on Wednesday, 8 April 2026.
Jasamarga also advises road users to be cautious, pay attention to traffic signs and instructions from on-site officers, plan their travel time and routes, and ensure sufficient balance on their electronic cards for smooth journeys.
The following are the repair points:
- Scrapping, Filling, and Overlay (SFO) Works
- Towards Jakarta
Lanes 1, 3, and 4, KM 24+930 to 17+700, at 13 work points, to be carried out from Tuesday, 7 April 2026 at 22:00 WIB until Tuesday, 21 April 2026 at 05:00 WIB.
- Towards Tangerang
Lane 4, KM 17+040 to 17+285, to be carried out from Wednesday, 14 April 2026 at 22:00 WIB until Thursday, 15 April 2026 at 05:00 WIB.
- Pavement Reconstruction Works
Towards Jakarta
Outer Shoulder Lane and Lanes 1-2, Karang Tengah Off Ramp, at 2 work points, to be carried out from Friday, 10 April 2026 at 06:00 WIB until Saturday, 11 April 2026 at 05:00 WIB.
Lane 2, KM 24+915 to 24+760, at 2 work points, to be carried out from Saturday, 11 April 2026 at 06:00 WIB until Monday, 13 April 2026 at 05:00 WIB.
Lane 2, KM 24+760 to 23+395, at 2 work points, to be carried out from Monday, 13 April 2026 at 06:00 WIB until Wednesday, 15 April 2026 at 05:00 WIB.
Lane 1, KM 23+845 to 23+545, at 6 work points, to be carried out from Wednesday, 15 April 2026 at 06:00 WIB until Friday, 17 April 2026 at 05:00 WIB.
Lane 1, KM 23+535 to 23+190, at 5 work points, to be carried out from Friday, 17 April 2026 at 06:00 WIB until Sunday, 19 April 2026 at 05:00 WIB.
Lane 2, KM 23+585 to 23+515, to be carried out from Sunday, 19 April 2026 at 06:00 WIB until Tuesday, 21 April 2026 at 05:00 WIB.
Towards Tangerang
Lane 2, Karawaci 2 On Ramp, to be carried out from Thursday, 9 April 2026 at 06:00 WIB to Monday, 13 April 2026 at 05:00 WIB.
Lane 2, KM 21+600 to 18+430, at 7 work points, to be carried out from Friday, 10 April 2026 at 09:00 WIB until Sunday, 26 April 2026 at 05:00 WIB.
Lanes 1-2, Karawaci 2 On Ramp, to be carried out from Monday, 13 April 2026 at 06:00 WIB until Saturday, 18 April 2026 at 05:00 WIB.
Lanes 1-2, Tangerang Toll Gate Exit Access, to be carried out from Saturday, 18 April 2026 at 06:00 WIB until Thursday, 23 April 2026 at 05:00 WIB.