Jambi-Rengat Toll Road Land Acquisition Targeted for Completion by End of 2026
Jambi Governor Al Haris has confirmed that the entire process of location determination through to land compensation data collection is targeted for completion by the end of December 2026.
The assurance was conveyed by the governor while chairing a coordination meeting on accelerating the construction of the Trans-Sumatra Toll Road (JTTS) Jambi-Rengat section, phase I of the Pijoan-Cinto Kenang-Merlung stretch spanning 67.45 kilometres.
“By the end of December, everything will be clear and clean — all land along the route traversed by the Jambi-Rengat toll road will be fully cleared,” said Jambi Governor Al Haris while opening the coordination meeting on accelerating the Jambi-Rengat toll road construction in Jambi City on Tuesday.
The governor explained that specifically for location determination, the government has set a deadline of 5 September 2026, so that the compensation process can be completed within the same year. The hope is that construction of the Jambi-Rengat toll road can commence in 2027.
According to him, accelerating the toll road construction requires collaborative work between Hutama Karya (HK), the National Land Agency (BPN), the National Road Implementation Agency (BPJN), and the regency governments of Muaro Jambi, Batang Hari and Tanjung Jabung Barat.
To that end, he urged all parties involved to maintain continuous coordination so that the national strategic programme in the field of inter-regional connectivity can be realised promptly.
Secretary to the Deputy for Connectivity Coordination at the Coordinating Ministry for Infrastructure and Regional Development, Rustam Efendi, said that accelerating connectivity cannot proceed in isolation and must involve multiple sectors.
The meeting, according to him, aims to ensure all stakeholders share the same understanding from both technical and administrative perspectives, in order to accelerate the implementation of the JTTS Jambi–Rengat section.
This is particularly important given that the project has been officially designated as a National Strategic Project (PSN) as stipulated in Appendix Number 14 of Coordinating Ministry for Economic Affairs Regulation Number 16 of 2025.
“This meeting is to align perceptions and build a shared commitment on how the acceleration of this JTTS can be implemented,” said Rustam.
The Jambi-Rengat toll road is planned to be divided into two sections. Section I runs from Simpang Ness to Cinto Kenang (Muaro Jambi Regency), spanning 18.75 kilometres.
Section II runs from Bukit Cinto Kenang to Merlung (Muaro Jambi Regency and Tanjung Jabung Barat), spanning 48.70 kilometres.
The construction of the JTTS is supported by foreign loan financing from the Islamic Development Bank (IsDB) and the Asian Infrastructure Investment Bank (AIIB).
The budget required to complete the construction of this toll road section reaches Rp17 trillion.
The areas to be traversed by the Jambi-Rengat toll road include Pijoan Urban Village, Tantan Village, Rantau Majo, Gerunggung, Bukit Baling, Suko Awin Jaya in Muaro Jambi Regency.
Additionally, Selat Village and Teluk in Batang Hari Regency, and Dusun Mudo Village in Muara Papalik District, Tanjung Jabung Barat Regency.
Source: jawawa.id (https://jawawa.id/newsitem/jambi-rengat-toll-road-land-acquisition-targeted-for-completion-by-end-of-2026-1786434902)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5688961/gubernur-pembebasan-lahan-tol-jambi-rengat-tuntasdesember-2026), translated from Indonesian