Jambi Prosecutors’ Office to Oversee Land Acquisition for 500 kV Transmission Project
Jambi (ANTARA) – The Jambi High Prosecutor’s Office is overseeing land acquisition and the provision of a right-of-way for the construction of the Muara Enim–New Aur Duri 500-kilovolt extra-high-voltage overhead transmission line in Muaro Jambi Regency.
Jambi High Prosecutor Sugeng Haryadi said in Jambi on Wednesday that the oversight was being carried out under the Strategic Development Security (PPS) programme in cooperation with state electricity company PT PLN’s South Sumatra Development Main Unit (UIP SBS).
“The commitment was marked by the signing of an integrity pact for strategic development security for projects under PLN UIP SBS,” he said.
Sugeng said the prosecutors’ support would focus on anticipating legal issues and obstacles that could affect the smooth construction of electricity infrastructure.
He said land acquisition and the provision of a transmission-line right-of-way were important processes that had to be carried out in accordance with applicable laws and regulations.
The Jambi High Prosecutor’s Office welcomed PLN’s confidence in its strategic development security work, particularly for the Muara Enim–New Aur Duri 500 kV line, which crosses Muaro Jambi Regency.
Separately, Suyanto, Director IV at the Attorney General’s Office Deputy Attorney General for Intelligence, said the project’s inclusion in the PPS programme had been preceded by the issuance of a strategic development security order on 23 September 2026.
The order, numbered SP.PPS-179/D/Dpp.3/09/2026, was followed by a request for the implementation of strategic development security dated 29 September 2026.
Suyanto said the PPS programme aimed to help anticipate and address potential threats, disturbances, obstacles and challenges that could disrupt the project.
The security measures are expected to support the orderly and accountable completion of construction in accordance with the law.
PLN UIP SBS General Manager Zaky Adikta said electricity transmission projects faced several challenges, particularly land acquisition, securing a right-of-way (RoW) and construction.
“Electricity infrastructure development often faces various challenges on the ground, from land acquisition and securing a right-of-way (RoW) to the construction process,” he said.
The Muara Enim–New Aur Duri 500 kV project is part of the development of Sumatra’s main electricity transmission network, with its contract value reported at around Rp2.68 trillion.
The project, previously undertaken by PT Waskita Karya (Persero) Tbk, encountered delays because of the contractor’s funding problems.
In March 2024, PLN said it was targeting the transmission line to begin operating by the end of 2026, following construction delays.
The Muara Enim–New Aur Duri 500 kV line is designed to strengthen electricity transmission from power-generation centres in South Sumatra to other parts of Sumatra, including Jambi.
The Jambi prosecutors’ oversight of land acquisition and right-of-way preparation is one measure intended to support the continuation of the strategic transmission project.
Zaky said PLN was prioritising the completion of several strategic projects to strengthen Sumatra’s interconnected electricity system.
Alongside the Muara Enim–New Aur Duri 500 kV line, another project being prioritised by PLN UIP SBS is the construction of the Betung–Kenten 275 kV transmission line.
Both projects are expected to improve the reliability of the transmission network and support electricity transfers between regions in Sumatra.
“This construction is not just about bringing electricity; it is also about providing energy for economic growth and improving people’s welfare, particularly in Jambi Province,” Zaky said.
The Jambi High Prosecutor’s Office said PPS support was intended to ensure strategic infrastructure development proceeded in accordance with the law, including by resolving issues that could potentially impede the project.
Source: jawawa.id (https://jawawa.id/newsitem/jambi-prosecutors-office-to-oversee-land-acquisition-for-500-kv-transmission-project-1791957089)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5785181/kejati-jambi-kawal-pembebasan-lahan-proyek-sutet-500-kv), translated from Indonesian