Jakarta's Casablanca Flyover Still Months Away
The Jakarta Globe
photo: The state-owned contractor said on June 3 that it was now targeting September for the completion of the project. (JG/Yudhi Sukma Wijaya)
Despite claiming on June 4 that the flyover linking Kampung Melayu and Tanah Abang would be completed by June 17, the state-owned company contracted to build the road told the Jakarta Globe today that it will not be open for months.
“The physical construction of the project may take another one or two months, followed by finishing jobs,” said Firmansyah Ibnu, project manager at Istaka Karya.
The firm said that the latest stumbling block to finishing the project, which it claimed was “90 percent complete,” was the arrival of a heavy-support machine from Taiwan.
“The purchase was made last week,” Firmansyah said. “It will arrive one month after we purchased it.”
The company said that the machine was necessary because existing equipment was too wide to preclude heavy traffic congestion on the streets below the incomplete section.
We were not able to confirm on Thursday why the company had made no mention of the purchase in its June 4 comments, when it said the project would be completed in a matter of days.
Jakarta Deputy Governor Basuki Tjahaja Purnama confirmed that the city was aware of the delay.
“There are parts that have yet to be concreted because they need specific heavy machinery as they cannot just pour concrete without causing congestion,” Basuki said.
Construction began in 2010 on a road — slated to cost around $90 million in total — that would alleviate congestion on Jalan Casablanca, a major retail center with several new shopping malls rubbing shoulders with longstanding, more down-at-heel tenants.
Despite assessments by the World Bank indicating that the growth in car and motorcycle sales could cause total gridlock in Jakarta as early as next year, a project that is fundamental to the city’s traffic-management has been characterized by delayed payments, unpaid workers, periods of inactivity, poor government oversight and broken promises by the company in charge.
“We’re looking at September to finish the construction,” Firmansyah said.
Source: jawawa.id (https://jawawa.id/newsitem/jakartas-casablanca-flyover-still-months-away-1372784400)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/news/casablanca-flyover-still-months-away/)