Jakarta MRT North-South Tunnel Breakthrough Connects Bundaran HI to Kota
Jakarta (ANTARA) - PT MRT Jakarta (Perseroda) has completed construction of the roughly 5.8-kilometre northbound tunnel connecting Bundaran HI Bank Jakarta Station to Kota Station, meaning Phases 1 and 2A of the north-south line are now linked, marking an important milestone in the project’s progress.
“With this achievement, the northbound tunnel of approximately 5.8 kilometres now connects Phase 1 and Phase 2A of the MRT Jakarta north-south line,” said Weni Maulina, Construction Director of PT MRT Jakarta (Perseroda), in Jakarta on Thursday.
Weni said the successful completion of the northbound tunnel excavation is an important milestone in the construction of MRT Jakarta Phase 2A, achieved in line with the established targets.
The completion was marked by a breakthrough moment, when tunnel boring machine 1 successfully reached the end point of the excavation and broke through the southern side of Mangga Besar Station.
PT MRT Jakarta (Perseroda) and its contractor teams used three tunnel boring machines to build the northbound tunnel of the Phase 2A north-south line.
Each machine worked according to its contract package: CP201 from Bundaran HI Bank Jakarta Station to Harmoni, CP202 from Harmoni to Mangga Besar, and CP203 from Mangga Besar to Kota.
At the breakthrough point on the southern side of Mangga Besar Station, the northbound tunnel lies at a depth of up to 28 metres below ground level.
“This achievement makes it the deepest underground rail tunnel in Indonesia, alongside the tunnel at Sawah Besar Station. A milestone in civil construction in Indonesia,” she said.
Tunnel boring machine 1, working on CP202, built the tunnel between Harmoni and Sawah Besar Stations of around 395 metres, as well as the 800-metre connecting tunnel between Sawah Besar Station and Mangga Besar Station.
To connect the two stations, tunnel boring machine 1 crossed beneath the canal located between Jalan Gajah Mada and Jalan Hayam Wuruk.
According to her, this achievement is the result of careful planning, good coordination, and the hard work of all parties involved in the construction of MRT Jakarta Phase 2A. The excavation of the northbound tunnel was completed in line with the set targets.
“This success is an important step towards completing the subsequent construction stages so that the project can continue on schedule,” she said.
The construction teams of PT MRT Jakarta (Perseroda) and its contractors are currently completing the southbound tunnel from Kota to Bundaran HI.
The target is for all Phase 2A north-south line tunnels to be completed in Q4 2026.
As of 25 June 2026, construction progress on Phase 2A has reached 61.8 per cent.
PT MRT Jakarta (Perseroda) is targeting the completion and operation of Phase 2A of the north-south line for the first segment, Bundaran HI–Monas, by the end of 2027, while the second segment through to Kota is targeted for the end of 2029.
Source: jawawa.id (https://jawawa.id/newsitem/jakarta-mrt-north-south-tunnel-breakthrough-connects-bundaran-hi-to-kota-1783590958)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5642313/stasiun-mrt-bundaran-hi-kota-telah-terhubung-lewat-terowongan-utara), translated from Indonesian