Jakarta Could Take Over Monorail Project if Delays Continue: Basuki
The Jakarta Globe By Hotman Siregar & Lenny Tristia Tambun
The capital’s outspoken Deputy Governor Basuki Tjahaja Purnama criticized continued delays of the Jakarta monorail project on Thursday, threatening to place the mass transit line under city control if construction fails to commence.
The capital’s administration is currently assembling a city-owned company to manage the expanding TransJakarta bus network, Basuki said. The same company could also oversee the monorail project if the Jakarta Monorail consortium continues to move at a sluggish pace, he said.
“We did everything we could to revive the project,” the deputy governor said. “We approved anyone who wanted to build [the monorail], But if they fail to complete the project, they won’t be refunded.”
Under the terms of the new contract offered to Jakarta Monorail, the company has three years to complete the construction project. If the company fails to finish by deadline, the city administration can seize ownership of all partially completed infrastructure, Basuki said.
“The old cooperation agreement didn’t mention that, so we offered them a new contract and they will have to discuss it,” he said. “If the project gets stuck, everything will become ours.”
The city would also have the right to resume the project without the involvement of Jakarta Monorail.
“Continuing the construction [without Jakarta Monorail] would benefit us, because they are now halfway into it,” Basuki said.
The official ground-breaking ceremony for the project took place on Oct. 16 last year, but since then little work has been done.
Basuki said on Monday that he suspected that Jakarta Monorail, as the developer, lacked the necessary funds to complete the project and pay off state construction company Adhi Karya.
Jakarta Monorail wants to use the partially constructed support pillars erected during a previous failed attempt to bring the capital a monorail, but they first have to purchase the structures from Adhi Karya at a cost of Rp 193 billion ($16.4 million).
The half-built concrete pillars currently line Jalan Rasuna Said in South Jakarta and Jalan Asia Afrika in Central Jakarta.
The project is estimated to cost Rp 1.7 trillion and is expected to run in 2016.
Policy analyst Agus Pambagio said the lack of progress on the monorail project highlighted how such a venture was unfeasible for the private sector to carry out. He cited similar projects in Malaysia, Australia and Japan, where the companies responsible for the construction of monorail lines ended up losing money and were eventually compelled to hand the project over to the government.
Agus also said the monorail was far from the ideal mass transportation solution that Jakarta needed, noting that its short trains could not carry as many people as a system like the mass rapid transit rail line, which is also being built in Jakarta.
“It’s not a feasible mass transportation option, the construction cost is too high, and all this will have an affect on the prices of tickets,” Agus said. “Who would want to pay Rp 30,000 for a short-distance trip on the monorail?”
Source: jawawa.id (https://jawawa.id/newsitem/jakarta-could-take-over-monorail-project-if-delays-continue-basuki-1392915600)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/news/jakarta/jakarta-could-take-over-monorail-projectif-delays-continue-basuki/)