Jakarta Approves Six New Toll Roads
TEMPO.CO
JAKARTA -- The Jakarta provincial government has finally approved the construction of six new toll roads. The project, worth more than Rp 40 trillion, will even be fast-tracked simultaneously, rather than just on two sections as in the original approved plan.
“The aim is to speed things up so they can be used during the 2018 Asian Games,” said Andi Baso Mappapoleonro, head of the Jakarta Regional Development Planning Agency, at City Hall yesterday.
Andi explained that approval for the construction of all six toll-road sections was given through an agreement made before Lebaran, specifically on 25 July. The agreement was signed by Jakarta Regional Secretary Saefullah, Toll Road Regulatory Agency head Ahmad Ghani Ghazali Akman, and PT Jakarta Tollroad Development president director Frans Sunito.
The six toll-road sections to be built are Semanan-Sunter, Sunter-Pulo Gebang, Duri Pulo-Kampung Melayu, Kemayoran-Kampung Melayu, Ulujami-Tanah Abang, and Pasar Minggu-Casablanca, covering a total of 69.77 kilometres. According to the plan, all the toll-road sections will be equipped with public bus lanes, in accordance with the condition attached to the approval given by Jakarta Governor Joko Widodo to the first two sections last year.
Andi added that all the toll-road sections would be elevated above roads owned by the Jakarta provincial government. The Jakarta government would acquire land to provide more space at the project sites. “Many of the roads we own are not yet as wide as planned. So we will also acquire land to widen those roads,” he said.
Frans said the pace of toll-road construction depended greatly on the provision of that land. It also depended, of course, on permits determining when the tender could be held. “Investors will not dare to build if there is no certainty over the land,” he said when contacted separately yesterday.
Frans added that, because the construction would be built above the highway, the land that had to be acquired would not be extensive. The only land to be acquired would be for toll gates or entry and exit ramps, as well as areas where the roads intersect with other land.
Frans projected that if land acquisition and permits were completed as targeted in March or April 2015, construction could begin in July 2015. “If we can start in 2015, we are optimistic construction will be completed in 2018, in time for the Asian Games,” he said.
The plan for the six new toll-road sections stalled last year after Jokowi rejected it, on the grounds that traffic congestion in Jakarta was projected to become worse. Later, he decided to accept only two sections for construction to be prioritised: Semanan-Sunter and Sunter-Pulo Gebang.
At the time, he said the two would provide access to Tanjung Priok Port that could be used by large trucks and containers. “So logistics will be helped by that route,” Jokowi said.