Jakarta Administration to Tidy 3 Kilometres of Tangled Cables in Kembangan
Jakarta (ANTARA) – The West Jakarta Bina Marga Sub-agency, in collaboration with the Indonesian Telecommunications Network Operators Association (APJATEL), began organising overhead cables on Jalan Kembangan Raya in South Kembangan, Kembangan district, West Jakarta, on Thursday.
“The cable work on Jalan Kembangan Raya began with the removal of cables along a three-kilometre stretch,” said Ahmad Sapii, head of the Urban Utilities Facilities and Infrastructure Maintenance Subgroup at the Jakarta administration’s Bina Marga Agency, in Jakarta on Thursday.
Ahmad said the utility-cable programme in West Jakarta covers six roads, with work extending a total of 15.5 kilometres.
The six roads are Jalan Meruya Selatan, covering 1,100 metres; Jalan Utan Jati, 6,000 metres; Jalan Kusuma, 1,600 metres; Jalan Brigjen Katamso, 2,600 metres; Jalan Kembangan Raya, 3,000 metres; and Jalan Kedoya Pilar, 1,200 metres.
“After Jalan Kembangan Raya, cable work will continue on the 1.2-kilometre stretch of Jalan Kedoya Pilar on 12 November 2026,” he said.
During the work, operators will be consulted about cables that remain in use.
“The work will be carried out in stages, through cutting and tidying the cables, followed by relocating the network underground,” he said.
Ahmad added that the work targets fibre-optic and telecommunications networks.
“Electricity cables require separate technical planning with the state-owned electricity company PLN before they can be moved,” he said.
Nirwono Yoga, a special adviser to the Jakarta Governor on development and urban planning, said the cable work followed an instruction from Jakarta Governor Pramono Anung through the 5M movement.
The movement includes cutting unused cables, requiring operators to relocate their networks independently, removing dead cables and raising cables hanging too low to prevent hazards to road users and pedestrians.
“The work is also being carried out simultaneously in all five administrative areas of Jakarta. In West Jakarta, cable work will cover approximately 15 kilometres,” he said.
He added that work on Jalan Kembangan Raya would proceed in stages, from removing overhead cables to dismantling poles that were no longer in use. The work is expected to be completed within two to three weeks.
“We hope this work will make it more comfortable for people to use the pavements and roads, improve mobility and enhance the cityscape by reducing the tangle of overhead cables,” he said.
Source: jawawa.id (https://jawawa.id/newsitem/jakarta-administration-to-tidy-3-kilometres-of-tangled-cables-in-kembangan-1793883204)