Jagorawi Toll Road Repairs: Note the Schedule and Locations

| | Source: KOMPAS Translated from Indonesian | Infrastructure
Jagorawi Toll Road Repairs: Note the Schedule and Locations
Image: KOMPAS

JAKARTA - The comfort and safety of toll road users are once again the priority for the managers of the Jakarta-Bogor-Ciawi Toll Road (Jagorawi) segment.

Jasamarga Metropolitan Tollroad (JMT), through its Representative Office 1, along with PT Jasamarga Tollroad Maintenance (JMTM) as the maintenance service provider, has officially resumed road repair works on this, Indonesia’s oldest toll road.

“The repairs are being carried out to maintain compliance with the Minimum Service Standards (SPM) for toll roads and to improve the safety and comfort of road users,” said Alvin in his official statement.

The road maintenance works on the Jagorawi Toll Road segment will be carried out as follows:

  1. Pavement Reconstruction Works

Towards Jakarta

  • Outer Shoulder Lane, Off Ramp GT Taman Mini, to be carried out on Monday, 6 April 2025 at 22:00 WIB until Wednesday, 8 April 2026 at 05:00 WIB.

Towards Pondok Indah

  • Lane 1, Kanalisasi Pasar Rebo, to be carried out on Monday, 6 April 2025 at 10:00 WIB until Thursday, 9 April 2026 at 05:00 WIB;

  • Lane 2, Kanalisasi Pasar Rebo, to be carried out on Thursday, 9 April 2025 at 10:00 WIB until Saturday, 11 April 2026 at 05:00 WIB.

Towards Ciawi

  • Lane 1, KM 28+291 to KM 28+398, to be carried out on Monday, 6 April 2026 at 22:00 WIB until Tuesday, 7 April 2026 at 04:00 WIB;

  • Lane 1, KM 28+300 to KM 28+500, to be carried out on Tuesday, 7 April 2026 at 22:00 WIB until Wednesday, 8 April 2026 at 04:00 WIB;

  • Lane 1, KM 31+300 to KM 31+500, to be carried out on Wednesday, 8 April 2026 at 22:00 WIB until Thursday, 9 April 2026 at 04:00 WIB;

  • Lane 2, KM 33+200 to KM 33+400, to be carried out on Thursday, 9 April 2026 at 22:00 WIB until Friday, 10 April 2026 at 04:00 WIB;

  • Lane 3, KM 33+200 to KM 33+400, to be carried out on Sunday, 12 April 2026 at 22:00 WIB until Monday, 13 April 2026 at 04:00 WIB.

Towards Jakarta

  • Lane 2, KM 29+811 to KM 29+561, to be carried out on Friday, 10 April 2026 at 22:00 WIB until Saturday, 11 April 2026 at 04:00 WIB;

  • Lane 2, KM 29+561 to KM 29+311, to be carried out on Saturday, 11 April 2026 at 22:00 WIB until Sunday, 12 April 2026 at 04:00 WIB.

“The lanes subject to works will be temporarily impassable during the construction period, but other lanes can be used for traffic,” said Alvin.

Therefore, drivers passing through are urged to be careful, pay attention to traffic signs and directions from on-site officers. To avoid congestion, it is advisable to adjust travel times and routes, as well as ensure sufficient balance on electronic toll cards.