Indonesian Political, Business & Finance News

Italian Oil and Gas Company Discovers Jumbo Reserves in Indonesia, Operations to Begin in 2028

| Source: CNBC Indonesia Translated from Indonesian | Energy
Italian Oil and Gas Company Discovers Jumbo Reserves in Indonesia, Operations to Begin in 2028
Image: CNBC Indonesia

Jakarta, CNBC Indonesia - The Ministry of Energy and Mineral Resources (ESDM) is accelerating the development of a giant gas reserve discovery by the Italian company Eni in the Geliga-1 exploration well, Ganal Block, Kutai Basin, offshore East Kalimantan.

The Director General of Oil and Gas (Dirjen Migas) of the Ministry of ESDM, Laode Sulaeman, explained that the government continues to provide support for the administrative requirements of the oil and gas company.

The government targets the giant gas reserve discovery of 5 trillion cubic feet (TCF) to become operational starting in 2029. “At most, we strengthen it so that the ENI process can be accelerated. That means if there are still permits or other administrative matters needed, we help to speed it up,” he said when met at the Ministry of ESDM office in Jakarta, quoted on Tuesday (5/5/2026).

Laode stated that the government continues to strengthen coordination so that the gas field development process does not encounter obstacles.

Although the field development plan or Plan of Development (POD) has been approved, the government assesses that supervision must still be carried out during the infrastructure preparation phase. This is to meet the timeline so that the production phase can start right on schedule in the 2028-2029 period.

“Yes, but the process is still ongoing. Everything is targeted for 2028-2029. That must be pursued,” he revealed.

To date, Laode said no regulatory obstacles have been found that disrupt ENI’s operational activities in the field. However, the government remains open to consultations with the company if there are unforeseen challenges that require acceleration at the central level.

“If they see any challenges or obstacles, we are ready to help speed it up,” he concluded.

Previously, the Minister of Energy and Mineral Resources (ESDM), Bahlil Lahadalia, revealed a new oil and gas discovery in East Kalimantan by Eni, estimated to add domestic condensate production by up to 150,000 barrels per hour (bph).

“We just found a new block in East Kalimantan obtained by Eni. That’s 5 TCF. Previously there were 2 TCF,” he said at the IPB Alumni Synergy for the Nation event, quoted on Monday (4/5/2026).

According to Ministry of ESDM data, this production comes from the Geliga Block, East Kalimantan. The project is projected to produce 90,000 bph of condensate in 2028, increasing to 150,000 bph in 2030.

Not only condensate, the gas production previously projected at 600-700 million standard cubic feet per day (MMSCFD) is set to increase to 2,000 MMSCFD in 2028. It will develop further in 2029 to reach 3,000 MMSCFD.

“Then it can produce around 375 million equivalent barrels per day for condensate. So in 2028 for this block, we can produce 2,000 to 2,500 MM, and in 2029 we target 3,000 MM for gas,” he explained.

“And in 2029-2030, we can add around 150,000 barrels per day for condensate. This is sometimes using field knowledge. It can’t be done, this is field science,” he clarified.

For the record, the Geliga well was drilled to a depth of about 5,100 metres in water depths of around 2,000 metres. This discovery extends ENI’s record of successful exploration in the Kutai Basin, following the large reserve find in Geng North in 2023 and the Konta-1 well discovery in 2025. The results of this discovery affirm the significant potential of the gas system in that basin as well as the stability of resources in the area.

The Geliga discovery occurred after the final investment decision (FID) for several gas projects, namely Gendalo and Gandang (South Hub), as well as Geng North and Gehem (North Hub).

For its development, the North Hub project will use a new floating facility (Floating Production Storage and Offloading/FPSO). Its capacity reaches 1 billion cubic feet of gas per day (bscfd) and 90,000 barrels of condensate per day (bpd). In addition, this project will also utilise existing facilities, including the Bontang LNG plant.

Besides the Geliga well, Bahlil also mentioned the discovery before Geliga, namely the Gula well, which produced around 2 TCF of gas and 75 million barrels of condensate. From both wells, the initial estimate of the combined Geliga and Gula resources has the potential to generate additional production of up to 1,000 mmscfd of gas and 90,000 bpd of condensate.

In addition to impacting the increase in national oil and gas reserves, the jumbo gas discovery in the Ganal Block also opens opportunities for accelerating the development of integrated gas infrastructure. ENI is currently evaluating a development scheme that synergises with the North Hub project and existing facilities such as the Bontang LNG plant, to speed up the monetisation of the discovery and optimise added value for the country.

More from 5 May 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/italian-oil-and-gas-company-discovers-jumbo-reserves-in-indonesia-operations-to-begin-in-2028-1777960641)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20260505110706-4-732305/perusahaan-migas-italia-temukan-cadangan-jumbo-di-ri-beroperasi-2028), translated from Indonesian
Print