Irregularities in the Hambalang Project [Tempo Commentary]

| Source: Tempo Interactive

Tempo.co

Audit Board (BPK) results show how riddled the Hambalang project is with irregularities. The development of the sports center in Sentul, West Java, seemed to have been forced. As a result, the Corruption Eradication Commission must uncover all aspects of this project.

During the second phase of audit investigations, the BPK reached a conclusion: the Hambalang project should not have continued because it was constructed on fragile soil. However, the project carried on and the budget was even blown up to Rp2.5 trillion. The state is estimated to have suffered losses amounting to more than Rp471.7 billion due to this recklessness.

So far, the Corruption Eradication Commission (KPK) has only charged a few suspects over the case, including former Youth and Sports Minister Andi Mallarangeng and his subordinate, a former Adhi Karya official as the contactor, and former Democratic Party chairman Anas Urbaningrum, when in fact, there are many more other figures involved.

Based on the latest audit results, the BPK also discovered some oddities. First, it was the removal of Finance Minister’s Decree No. 56/PMK.02/2010 which was replaced with PMK No.194/PMK.02/2011 about how to submit the approval for a multi-year contract for the procurement of government goods/services. The old regulation contained a stipulation that a technical recommendation from the related minister and approval from the House of Representatives (DPR) was required to be able to obtain a multi-year contract. Meanwhile, the new regulation removed this condition.

Second, members of the House were involved in the approval of the budget used for the Hambalang project. A number of legislators signed the approval for the 2012 amended state budget allocation amounting to Rp600 billion even though it was never discussed with the Sports Ministry.

The third finding was Dutasari Citralaras, the subcontractor for mechanical and electrical works on the Hambalang project, was suspected to have marked up the value of the project, amounting to Rp324.5 billion – the largest value for the project compared to 38 other Hambalang subcontractors.

Fourth, high-ranking officials in this company are suspected to have forged their shareholders deeds. Athiyyah Laila, Anas Urbaningrum’s wife, was initially named as commissioner at Dutasari. However, her name did not appear on the 2009 deed. The latest deed is suspected to be a forgery and is not listed at the Justice and Human Rights Ministry because it was recently created.

These findings must be immediately investigated by the KPK and other law enforcers. The police, for example, must investigate the forged deed further. According to the criminal code, the notary and client proved of creating a forged deed can be jailed.

The KPK should also immediately investigate the involvement of legislators, officials at the Finance Ministry and Hambalang subcontractors who have been left untouched. Letting time take its course on this case will cause more problems in the investigation because there it creates more opportunities for the corruptors to conceal their unlawful acts. (*)

More from 28 August 2013 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/irregularities-in-the-hambalang-project-tempo-commentary-1377622800)
Originally published by Tempo Interactive (http://en.tempo.co/read/news/2013/08/27/080507960/Irregularities-in-the-Hambalang-Project)
Print