Indonesia's Giant EV Battery Plant to Operate in July 2026, Here's Its Capacity

| Source: CNBC Indonesia Translated from Indonesian | Industry
Indonesia's Giant EV Battery Plant to Operate in July 2026, Here's Its Capacity
Image: CNBC Indonesia

The Indonesia Battery Corporation (IBC) has confirmed that the electric vehicle (EV) battery plant owned by PT Contemporary Amperex Technology Indonesia Battery (CATIB) in Karawang, West Java, will begin operations by the end of July 2026.

PT CATIB is a joint venture between the Indonesia Battery Corporation (IBC) and CBL, a subsidiary of China’s largest battery manufacturer, Contemporary Amperex Technology Co. Limited (CATL).

IBC President Director Aditya Farhan Arif stated that the first phase of the EV battery plant’s production capacity will reach 6.9 gigawatt hours (GWh). Construction of the facility is proceeding according to schedule, with operations targeted for late July 2026.

“The first capacity we will install is 6.9 GWh and, God willing, it is still on schedule. We are targeting the end of July 2026. Currently, progress has reached 90%, so we are quite optimistic that we will achieve the target,” Aditya told CNBC Indonesia on Tuesday.

Aditya explained that once commercial operations commence, the plant will not face difficulties in finding markets as buyers are already secured. He noted that the EV battery industry concept was built based on existing demand, allowing production to begin immediately. “In principle, buyers are ready, so when we are ready for commercial use, we can proceed directly with production. In fact, trial production is already underway at the PT CATIB plant.”

Furthermore, he explained that the nickel value chain, from the mining sector to the final battery, involves a lengthy process. The stages begin with mining, followed by primary processing, then the production of battery materials, and finally, battery production.

PT CATIB, he noted, sits at the most downstream position in this value chain. He emphasised that PT CATIB’s presence is a vital component of the overall integrated nickel industry ecosystem.

“The capacity for CATIB in this first phase is 6.9 GWh, and we will soon expand it to at least 15 GWh. If we convert 15 GWh into electric vehicles, it is roughly equivalent to approximately 250,000 EVs,” he added.

Integrated EV Battery Factory

As is well known, Indonesia is currently building an integrated EV battery factory ecosystem, claimed to be the largest in Asia. This is supported by the vast reserves of nickel, the primary raw material for battery components.

This upstream-downstream integrated battery ecosystem project is operated by PT Aneka Tambang (Antam), Indonesia Battery Corporation (IBC), and the Chinese company Ningbo Contemporary Brunp Lygend Co. Ltd. (CBL), which is a joint venture involving CATL, Brunp, and Lygend.

The total initial investment for the entire integrated battery project reaches US5.9billion, orapproximatelyRp96.04trillion(assuminganexchangerateofRp16, 278perUS).

The project consists of six joint ventures (JV) ranging from upstream to downstream. JVs 1 to 3 represent the upstream battery ecosystem, while JVs 4 to 6 represent the downstream ecosystem.

Upstream:

JV 1: Nickel mining project by PT Sumberdaya Arindo (SDA) with a production capacity of 7.8 million wet metric tons (wmt) of saprolite and 6 million wmt of limonite, totaling 13.8 million wmt. Ownership is split between PT Antam (51%) and CBL (49%). This project has been in production since 2023.

JV 2: Nickel smelting facility (RKEF type) at PT Feni Haltim (FHT) with a capacity of 88,000 tons of refined nickel alloy per year. Ownership is split between CBL (60%) and PT Antam (40%). It aims to begin production in 2027.

JV 3: Nickel processing facility (HPAL type) at PT Nickel Cobalt Halmahera (HPAL JVCO) with a capacity of 55,000 tons of MHP per year. Ownership is split between CBL (70%) and PT Antam (30%). It aims to begin production in 2028.

Downstream:

JV 4: Battery material project producing cathode materials, cobalt sulphate, and ternary precursors with a capacity of 30,000 tons of lithium hydroxide, located in East Halmahera, North Maluku. Ownership is split between CBL (70%) and PT IBC (30%). It aims to begin production in 2028.

JV 5: Battery cell project by PT Contemporary Amperex Technology Indonesia Battery (CATIB) located in Artha Industrial Hill (AIH) & Karawang New Industry City (KNIC). This is divided into Phase 1 with a capacity of 6.9 GWh/year and Phase 2 with 8.1 GWh/year, totaling 15 GWh/year. Ownership is split between CBL (70%) and PT IBC (30%). Phase 1 is targeted for 2026, and Phase 2 for 2028.

JV 6: Battery recycling project located in East Halmahera, North Maluku, with a capacity of 20,000 tons of metal per year. Ownership is split between CBL (60%) and PT IBC (40%). It aims to begin production in 2031.

More from 23 June 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/indonesias-giant-ev-battery-plant-to-operate-in-july-2026-heres-its-capacity-1782226284)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20260623170249-4-745122/pabrik-baterai-ev-raksasa-ri-beroperasi-juli-2026-segini-kapasitasnya), translated from Indonesian
Print