Indonesian Power Project on Hold as Opponents Dig in Their Heels

| Source: Nikkei

Nikkei Report

Plans by government and businesses in Indonesia and Japan to build a large coal-fired power plant on the island of Java have hit a roadblock amid protests by residents and environmentalists.

"I don't want to sell this land even if they offer more money," said an elderly farmer standing by rice paddies on the Batang Regency coast. Flags saying "no power plant," which he says were provided by a nongovernmental organization, flap everywhere.

Such opposition has stalled purchases of land for the plant. Plans had called for construction to start in 2012 on a power station capable of supplying enough electricity to meet the needs of 13 million people. The facility was scheduled to come online in 2016, but to date, not even a loan agreement has been signed.

Financing for the $4 billion plant will be led by the Japan Bank for International Cooperation. Japanese partners Electric Power Development, or J-Power, and trading house Itochu will team with a local coal company to build the facility, which will sell electricity to state-run utility PLN for 25 years.

Unless a land purchase is completed, a loan agreement cannot be concluded. "We all intend to continue with the project," said a Japanese source. But the delay is diminishing the business prospects for the project.

Nongovernmental organizations, or NGOs, are powerful in Indonesia. Greenpeace and other groups are leading local residents in protesting the Batang project. Although plans have been set in motion to purchase more than 85% of the required land, some note that those holding the property rights for a key section of the project site are all influenced by the protesters. This raises the question of whether the planners had paid enough attention to the NGOs.

Under the agreement, land purchases are handled by the project operators. A group led by Japanese trader Marubeni, which lost the bidding for the J-Power-Itochu coalition, had focused on this point and chosen a different site that would have been "more costly for ground preparation but associated with fewer issues when purchasing," according to a source in the power industry. With the Batang project, the operators might have placed too much priority on cost early on, the source says.

Meanwhile, emotions are running high between residents who want to see the project started and those adamantly opposed to construction altogether. "Companies are now offering four times the price of what we sold, and that's unfair," said a man who already sold his property.

The planners, according to residents, engaged in almost no explanations or communication at the beginning, suggesting that the companies apparently prepared poorly and had unrealistic expectations about buying land.

More from 30 October 2014 โ†’

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/indonesian-power-project-on-hold-as-opponents-dig-in-their-heels-1414602000)
Originally published by Nikkei (http://asia.nikkei.com/Business/Trends/Indonesian-power-project-on-hold-as-opponents-dig-in-their-heels)
Print