Indonesia Optimistic Cepu will Deliver in 2014 Despite Hurdles
Platts
Indonesia's Cepu oil project -- which is critical to the country meeting its 1 million b/d oil output target by 2015 -- remains mired in construction delays, but ExxonMobil and upstream regulator SKK Migas are upbeat that it will ramp up and reach peak production of 165,000 b/d in 2014.
The project's stumbling blocks center around delays in the award and execution of engineering, procurement and construction contracts.
Erwin Maryoto, ExxonMobil Indonesia's vice president for government affairs, told Platts last week that the project faced schedule pressures in some areas, but he said the company was working with contractors and SKK Migas to identify ways to maximize 2014 production.
"[The project] has met many milestones including groundbreaking in December 2011 and the commencement of drilling, with Indonesian-constructed rigs in May 2013," Maryoto said. "The project is currently around 50% complete."
SKK Migas Secretary Gde Pradnyana also said there were several problems hampering Cepu's second-phase development but was upbeat it would hit peak production in 2014.
"The main problems [with] Cepu block's developments were land acquisitions and permits from local government, and these have nothing to do with technical issues," Pradnyana said, adding that the regulator and operators are "running fast" to achieve peak production in 2014.
PROBLEMS SINCE INCEPTION
The Cepu oil project took a long time to get off the ground due to protracted negotiations between Pertamina and ExxonMobil over issues including equity split and operatorship of the block. The two signed a production-sharing contract in September 2005 -- four years after the block's surprise major oil discovery at Banyu Urip in 2001.
Pertamina and ExxonMobil each took a 45% stake in the block, with the local governments sharing the remaining 10% equity.
Banyu Urip is estimated to contain more than 250 million barrels of oil. In April 2011, ExxonMobil announced a second oil discovery in the Cepu block, the Kedung Keris field, which it said would be an important addition to the oil resources recovered from the development.
However, the project has had a rocky start since coming on stream in December 2008, unable to maximize the 20,000 b/d design capacity of the initial production facilities because of technical problems and issues with evacuating the crude.
The block had been tipped to reach peak production of 165,000 b/d in March 2009, but delays in the award of EPC contracts has led to a five-year delay.
"We understand the importance of the Banyu Urip project and are committed to evaluating opportunities to enhance execution efficiency," Maryoto said.
ExxonMobil has increased production of oil from the Banyu Urip early production facility to over 26,000 b/d as of April 2013, Maryoto said. This represents a 2,000 b/d increase from the recent 2012 production levels and a total 6,000 b/d increase from its original design capacity of 20,000 b/d in 2009, according to Maryoto.
CONTRACTING DELAYS
The Cepu project involves five different EPC contracts, four of which are worth a total $1.25 billion and were awarded in 2011.
EPC-I covers construction of production facilities; EPC-II covers design and installation of a 72-km insulated pipeline; EPC-III covers construction of an offshore pipeline and mooring facilities; EPC-IV covers construction of a floating storage and offloading facility; and EPC-V involves building a reservoir to support the water injection technique to lift oil and gas, as well as other production-supporting facilities.
"Several of the EPC works have been delayed due to permit issues and issues surrounding the use of local contractors," Pradnyana said last week.
Elan Biantoro, head of SKK Migas' communication division, said Monday that the consequence of accelerating construction has resulted in the EPC-I contractors asking ExxonMobil to adjust the contract's value.
"They wanted the contract cost to be adjusted for speeding up construction as they have to increase their human resources and work-hours," Biantoro said. "But SKK Migas rejected the proposal, as it can influence the project's economics. We are still in discussion to resolve the problem."
GAS PROJECT
The Cepu block straddles the border between Central Java and East Java and is estimated to contain a total 600 million barrels of oil and 1.7 Tcf of gas.
Pertamina and its partners plan to spend a total $3.3 billion to develop Cepu's gas reserves, Pradnyana said in February.
The final investment decision for the gas project is expected to be made over 2015-2016 while EPC works are expected to start at the end of this year, he said.
Gas production from the Cepu gas project is expected to come on stream by 2017 with an output of 185,000 Mcf/d and condensate output of 3,000 b/d by 2019.
Pertamina and ExxonMobil Indonesia signed a heads of agreement in August 2011 on the Cepu gas project involving the development of Jambaran and Tiung Biru fields.
Both fields contain a total 1.2 TCF of recoverable gas reserves and 18.6 million barrels of condensate reserves, according to SKK Migas. Production lifespan is from 2017-2035.
--Anita Nugraha, newsdesk@platts.com
--Mriganka Jaipuriyar, mriganka.jaipuriyar@platts.com
--Edited by Meghan Gordon, meghan.gordon@platts.com