The Ministry of Marine Affairs and Fisheries (KKP) has revealed the progress of constructing a large-scale integrated shrimp pond complex in Palakahembi Village and Watumbaka Ward, Pandawai District, East Sumba Regency, Nusa Tenggara Timur (NTT). This project is touted as the largest shrimp pond model in Indonesia and a marker for aquaculture development no longer centred on Java island.

Director General of Aquaculture at KKP, TB Haeru Rahayu, stated that the construction of the shrimp ponds, with a total area of 2,150 hectares (equivalent to 22,150 football pitches) and a total investment of Rp 7.2 trillion, is ongoing. As of 31 March 2026, the pond plots for shrimp farming have begun to take shape.

“Currently, the process of building the shrimp pond plots has started, designed by a team we have appointed who are competent in the field, so that sustainability aspects will be very important later,” Haeru said during a press conference on Wednesday (1/4/2026).

Haeru added that within two years, the shrimp pond construction could be completed and operational.

“We are indeed planning this not just for a month, because building these ponds in such large numbers takes time; we hope to complete it within two years, and next year, God willing, some can already be operational,” he continued.

He also plans to accelerate the construction to meet the set timeline.

“We want to carry out accelerations; this is what we are consulting and discussing with our consortium partners who have been mandated to carry out this construction,” he explained.

Regarding the two clusters scheduled to operate this year out of the 12 prepared clusters, the exact timing remains uncertain as it is still tentative.

“Actually, the contract is for three years. But President Prabowo has asked the Minister of KKP to accelerate this. We are pushing for two years. Pray that we can guide this well. The initial design was to run two clusters first, but this is still very temporary. If possible, we finish everything; that would of course be much better,” he clarified.

The shrimp pond construction includes eight layouts to be built, from seawater pipeline networks to the shrimp ponds to other usage areas. First, the seawater intake pipeline network to the shrimp ponds covering 62 hectares (ha), where progress has reached 4.56%, consisting of the intake head, intake pipeline network, pump house, and reservoir. Second is the transmission pipeline, which has not yet been constructed. Third is the water storage and treatment tank covering 46 ha, with progress at 3.38%.

Fourth, the cultivation area covering 723 ha, where progress has reached 58.31%. This area will feature 12 maintenance pond clusters, 192 cluster tanks, 48 pond wastewater treatment plants (IPAL), and other facilities. Fifth is the wastewater treatment system or IPAL for the complex covering 60 ha, with progress at 4.41%. Sixth is the greening facilities area covering 339.4 ha, which has reached 24.94%. Seventh is the supporting industrial area covering 60 ha, which has reached 4.41%. Finally, the other usage area covering 724 ha remains unbuilt.

More from 1 April 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/indonesia-builds-giant-shrimp-pond-complex-the-size-of-2-150-football-pitches-here-1775026258)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20260401122341-4-723141/ri-bangun-tambak-udang-raksasa-seukuran-2150-lapangan-bola-di-sini), translated from Indonesian
Print