Indonesia Begins Development of 100 GW Solar Power, Electricity Price Estimated at 5-6 US Cents per kWh

| Source: CNBC Indonesia Translated from Indonesian | Energy
Indonesia Begins Development of 100 GW Solar Power, Electricity Price Estimated at 5-6 US Cents per kWh
Image: CNBC Indonesia

Jakarta, CNBC Indonesia - The government has officially commenced development of a 100 Giga Watt peak (GWp) solar power plant (PLTS) megaproject. Electricity from the solar facility is expected to cost around 5-6 US cents per kWh.

Minister of Energy and Mineral Resources Bahlil Lahadalia emphasised that this figure represents the cost of electricity production from solar panels, while additional costs will arise depending on the required energy storage capacity.

“For the PLTS alone that we are inaugurating now, the value is approximately 5 to 6 cents. However, that does not include batteries. The batteries will be added on top,” he said in his report during the inauguration of the 100 GWp PLTS programme in Jembrana Regency, Bali, as quoted on Wednesday (26/8/2026).

Bahlil explained that the final price determination will be influenced by the duration of battery usage required to maintain grid stability or base load. His ministry continues to calculate so that the integration between solar generation and battery systems remains economically competitive for both developers and consumers.

“The battery depends on whether you want 4 hours or 24 hours — the price will follow the duration of battery usage. Is that right, Mr PLN President Director? We must not make mistakes in front of the President,” he explained.

The megaproject is projected to require total investment of US$73 billion, equivalent to more than Rp1,140 trillion. Construction will be carried out over at least the next three years.

The project is expected to reduce the state’s energy subsidy burden by up to Rp73.9 trillion per year and absorb 5.52 million workers.

“From this total work, we can achieve annual subsidy efficiency of Rp73.9 trillion. It can create approximately 5.52 million jobs,” he stated.

Additionally, Bahlil reported that specifically in the Bali region, the PLTS development will replace the role of diesel power plants that have been in use. This is considered crucial to support Bali’s image as an international tourist destination that prioritises green energy.

“Specifically for Bali, by using 1,000 Mega Watts we can achieve efficiency of 0.6 million kilolitres of diesel fuel currently used by PLN. All this time Bali has still been using diesel power plants. So it is no wonder that we are doing this in Bali because the campaign is green energy,” he said.

The programme also includes economic empowerment for coastal communities and remote islands through a productive use of energy scheme. In several locations, the PLTS will be integrated with cold storage facilities, ice-making machines, and electric boat charging stations for local fishermen.

“If the sun is Indonesia’s sun, the solar panels are made by the hard work of the Indonesian people, and the electric batteries are produced from the sweat of Indonesian workers, then this solar energy is Indonesia’s energy, the energy of Ibu Pertiwi,” he concluded.

Based on data from the Ministry of Energy and Mineral Resources, initial development is focused on the first 14 projects with a total capacity of 5,216 Mega Watt peak (MWp) spread across various regions. The following is a list of strategic PLTS projects included in the tender and construction phases:

Projects Ready for Tender:

  • Jatiluhur Floating PLTS (West Java): 1,688 MWp

  • Cirata Floating PLTS (West Java): 1,250 MWp

  • Jatigede Floating PLTS (West Java): 636 MWp

  • PLTS+BESS Madura Cluster (East Java): 605 MWp

  • Bali PLTS (Gilimanuk): 300 MWp

  • Purwakarta Land Bank PLTS (West Java): 69 MWp

Construction & Groundbreaking Projects:

  • Banyuwangi PLTS (East Java): 130.2 MWp (Groundbreaking)

  • Pasuruan PLTS (East Java): 132 MWp (Groundbreaking)

  • Gajah Mungkur Floating PLTS (Central Java): 134.2 MWp (Groundbreaking)

  • Karangkates Floating PLTS (East Java): 133 MWp (Construction 56.54%)

  • Saguling Floating PLTS (West Java): 92 MWp (Construction 44.4%)

  • Tembesi PLTS (Batam): 46 MWp (Construction 65%)

  • Sembur Village PLTS (Batam): 0.92 MWp

  • Rengit Island PLTS: 0.078 MWp

More from 26 August 2026 →

Cite this article