IKN Project Funding Update as of August 2026: 29% Private Investment, 19% State Budget
The Nusantara Capital City (IKN) development project is financed through a number of schemes, ranging from the State Revenue and Expenditure Budget (APBN), government and business entity cooperation (KPBU), private investment, to grants.
Head of the IKN Authority Basuki Hadimuljono said the total funding for the IKN project currently stands at Rp257.56 trillion. Of that amount, Rp48.8 trillion or 19% comes from the APBN.
The APBN funding is divided into three construction batches.
The first batch in 2025 covers the development of connectivity supporting investment, including the improvement of the KIPP 1B and 1C access roads spanning 12.1 kilometres as well as the arrangement of the Sepaku area. The first batch of construction has been 100% completed.
The second batch in 2025–2027 covers the construction of legislative and judicial institution offices as well as supporting infrastructure, such as the DPR, DPD, MPR, Supreme Court, Constitutional Court, and Judicial Commission buildings as well as roads in the KIPP 1A area. The average construction progress of the second batch has reached 13.6%.
“We have calculated that for the legislative, Rp48.8 trillion is needed. This is for the construction of buildings, areas and connectivity, and he [President Prabowo] agreed at the time and prepared [the allocation],” Basuki said when met after the 81st Indonesian Independence Day Flag Raising Ceremony at IKN, Monday (17/8/2026).
Meanwhile, the third batch, implemented in 2026–2028, covers the construction of housing for legislative, judicial, and civil servant personnel along with supporting infrastructure. The project is still in the tender preparation stage.
The second source of funding comes from the KPBU scheme with a value of Rp134.22 trillion. The funding covers two groups of projects, namely housing as well as roads and multi utility tunnel (MUT).
For the housing project, the government is cooperating with a number of business entities, including PT Intiland Development Tbk. (DILD), which will build 109 landed houses and 41 apartment towers.
Furthermore, private investment reached Rp74.54 trillion or around 29% of the total IKN funding. Basuki said there are 67 private investors who will develop various facilities, such as hotels, hospitals, shopping centres, restaurants, as well as sports and recreation facilities.
These investors include PT Dejem Nusantara Development, PT Dian Jaya Indonesia, and PT Starbright International Investment.
PT Dian Jaya Indonesia is a real estate company that is a subsidiary of Dian Development Co., Ltd. from South Korea. The company will develop apartments and hotels in WP KIPP Sub-WP 1B.
The construction of the project is planned to begin in the fourth quarter of 2026 on a land area of 33,201 square metres with an estimated investment value of Rp1.15 trillion.
“As for Star Bright, this is from China, building 4 residential and commercial towers. Work has already begun. The value is Rp1.2 trillion,” Basuki said.
The following is a breakdown of IKN development funding as of August 2026:
A. APBN Rp48.8 Trillion
Batch 1 (2025)
12.1 km improvement of KIPP 1B & 1C access roads
Sepaku area arrangement
Green open space arrangement
Batch 2 (2025–2027)
DPR Building
DPD Building
MPR Building
Plenary Session Building
Supreme Court Building
Constitutional Court and Judicial Commission Building
Supporting Offices
Legislative Area Roads
Judicial Area Roads
KIPP 1A Supporting Area Roads
KIPP 1B Retention Basin
KIPP 1C Retention Basin
Retention Pond
Drinking Water Pipeline Network
Batch 3 (2026–2028)
Housing for legislative, judicial, and civil servant personnel
Supporting infrastructure (roads & MUT, sanitation, drinking water, area arrangement)
B. KPBU Rp134.22 T
Housing Initiators
Intiland (109 landed houses, 41 apartment towers)
Nindya (8 apartment towers)
Guangxi – DMT (11 apartment towers)
Samsung C&T (21 apartment towers)
PJ-IC (20 apartment towers)
IJM-CHEC (20 apartment towers)
PT Hutama Karya (10 apartment towers)
Road & MUT Initiators
PT Sumber Mitra Jaya (17.67 km)
CSCEC (31.36 km)
PT Adhi Karya (15.48 km)
Nindya – Brantas (21.67 km)
CHEC – IJM (26.9 km)
Guangxi – DMT (21.04 km)
C. Private Investment Rp74.54 T (67 Investors)
PT Dejem Nusantara Development
PT Dian Jaya Indonesia
PT Starbright International Investment
PT Panca Karya Sentosa
PT Fajar Maju Karya Gemilang
PT Plataran Boga Rasa
PT Haupstadt Indonesia Borneo
PT Electronic City Indonesia
and others
D. Grants (10 grants in the form of physical development, studies, and capacity building)
MOLIT – grant smart city cooperation centre
UTSDA – grant ICC pilot project
UTSDA – grant enterprise architecture
ADB – Technical assistance E2W low carbon cluster strategy
ADB – Liveable and lovable city study
ADB – Support for water-sensitive city
KIAT – Nusantara urban mobility project
CLC – SSNUP 2026
BNPB & BPBD – disaster management equipment
Danone – CSR TPS3R
Source: jawawa.id (https://jawawa.id/newsitem/ikn-project-funding-update-as-of-august-2026-29-private-investment-19-state-budget-1786971050)
Originally published by ekonomi.bisnis.com (https://ekonomi.bisnis.com/read/20260817/9/1996901/update-pendanaan-proyek-ikn-per-agustus-2026-29-investasi-swasta-19-apbn), translated from Indonesian