IESR Supports Temporary Suspension of BDx Data Centre Construction in Jatiluhur
Jakarta (ANTARA) - The Institute for Essential Services Reform (IESR) supports the decision by the Governor of West Java to temporarily suspend the construction of the BDx Data Centre, an artificial intelligence (AI) data centre located in the Jatiluhur area, Purwakarta Regency.
“Development must continue while respecting the sustainability of water resources, electricity reliability, and the community’s right to access information,” said IESR Chief Executive Officer Fabby Tumiwa, as confirmed in Jakarta on Friday.
According to him, a project with such significant water and electricity requirements should not be undertaken before environmental and building permits are finalised and before the potential impacts are made known to the public.
Fabby stated that the organisation supports the West Java Provincial Government’s move to halt the data centre project due to unfulfilled licensing requirements. “We appreciate the firmness of the Governor of West Java regarding the suspension of the data centre project construction,” he added.
It is reported that BDx’s AI Campus 2 (CGK4) is planned to have a capacity of 640 megawatts (MW) and is situated approximately five kilometres from the Jatiluhur Reservoir. The groundbreaking ceremony was scheduled for 22 September 2026.
Six days later, following a sudden inspection by the Governor on 28 September 2026, the West Java Provincial Government halted construction work because the Environmental Impact Assessment (AMDAL) and Building Approval (PBG) had not yet been issued by the Purwakarta Regency Government.
He noted that the project demands extreme caution, as water requirements in the next development phase are estimated to reach 384 litres per second, equivalent to approximately 33,000 cubic metres per day or more than 12 million cubic metres per year. This water would be sourced from the Jatiluhur Reservoir, which serves as the backbone for paddy irrigation in West Java’s rice granary.
“A load of 640 MW, if operating at full capacity throughout the year, is equivalent to electricity consumption of up to approximately 5.6 terawatt-hours (TWh) per year,” he added.
Source: jawawa.id (https://jawawa.id/newsitem/iesr-supports-temporary-suspension-of-bdx-data-centre-construction-in-jatiluhur-1790906163)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5767767/iesr-dukung-penghentian-sementara-bdx-data-center-di-jatiluhur), translated from Indonesian