Humbang Hasundutan Begins Reconstruction of 3-Kilometre Damaged Road to Smooth Agricultural Distribution

| Source: Tempo (Indonesian) Translated from Indonesian | Infrastructure

The Humbang Hasundutan Regency Government is prioritising the reconstruction of the Parbotihan–Pulo Godang–Temba section, which was damaged by hydrometeorological disasters in late 202scale. This priority was outlined during an assistance session regarding the use of Additional Regional Transfers (TKD) alongside the Directorate General of Regional Financial Management of the Ministry of Home Affairs and the PRR Task Force on Wednesday, 1 July 2026.

According to the presentation by the Humbang Hasundutan Regency Public Works and Spatial Planning Department (PUPR), the 18.5-kilometre Parbotihan–Pulo Godang–Temba section serves as a link to the Central Tapanuli Regency and is the primary access route to the Onan Ganjang-Pakkat provincial road. Currently, the area suffers from approximately 937 metres of landslides, 2 kilometres of road damage, and 31 metres of damaged bridge.

This route is the main access for the community to agricultural areas, schools, health facilities, markets, and economic activity centres in the Pakkat District. It also serves as the primary route to the Seribu Gua tourist destination.

The PUPR Department has proposed the repair of a 3-kilometre road section with a required budget of Rp 23.78 billion, which includes the reconstruction of the damaged bridge.

The Head of Road and Bridge Development for Humbang Hasundutan Regency, Tulus Sipahutar, stated that previous handling has been limited to emergency measures. “Previous TKD funds could not be used to fix the damaged roads; they were only used for road retaining walls,” he said.

Tulus noted that the procurement process for physical works is underway. Some packages are being implemented through direct procurement mechanisms, while two other packages are using the e-Catalogue Mini Competition system and are currently in the document uploading stage.

“We are striving to ensure that by July 2026, all contracts are signed, and by October 2026 at the latest, approximately 85 per cent of the budget is utilised,” said Tulus.

To maintain community mobility, a Bailey bridge is being used as a temporary replacement for the damaged bridge. Meanwhile, road surface repairs are being conducted using sand and stone (sirtu) sourced from the disaster-affected area until permanent works begin.

The road reconstruction complies with the Circular Letter of the Minister of Home Affairs Number 900.1.3/1084/SJ, which regulates the use of Additional Regional Transfers. Point 4, Clause C specifies that disaster-affected regions may use the budget for post-disaster activities, including the repair of the affected environment and the reconstruction of public infrastructure.

The Sub-director of Region I of the Regional Budget Planning Directorate at the Ministry of Home Affairs, Fernando H. Siagian, reminded officials that all construction funded through Additional TKD must be implemented specifically in the disaster-affected areas. “We must ensure that if the damage is in District A, the assistance does not go to District B,” he warned.

It is hoped that the use of Additional TKD for this infrastructure project will restore inter-regional connectivity, smooth the distribution of agricultural products, normalise access to schools and health facilities, and accelerate the recovery of economic activities in the disaster-affected areas.

More from 2 July 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/humbang-hasundutan-begins-reconstruction-of-3-kilometre-damaged-road-to-smooth-agricultural-distribution-1783000568)
Originally published by Tempo (Indonesian) (https://nasional.tempo.co/read/2111590/perlancar-distribusi-hasil-pertanian-jalan-rusak-3-kilometer-di-humbang-hasundutan-mulai-rekonstruksi-lewat-tkd-tambahan), translated from Indonesian
Print