Heavy Rain Takes a Toll on Jakarta’s ‘Zero Pothole’ Plan
The Jakarta Globe By Fana SP Putra & Siprianus SP Hardum
photo: Motorcyclists navigating a damaged stretch of road in Dukuh Atas, Central Jakarta. (JG/Afriadi Hikmal)
Jakarta: Torrential rains have severely hampered the Jakarta administration’s plans to rid the capital’s pockmarked streets of potholes, a top public works official said on Monday.
Jakarta Governor Joko Widodo’s ambitious “zero potholes” plan failed to reach its goal in 2013 amid delays in the implementation of an electronic tender system. The governor, apologetic about the administration’s failure, pledge to repair the capital’s degraded roadways by the year’s end.
But the damaged caused by this year’s heavy rains have made repairing the roads something of a Sisyphean task for the city’s public works employees. The roads of Jakarta are paved with an asphalt “hotmix” that inevitably degrades with each rainy season, Ahmad Yazied, head of the road maintenance department at the East Jakarta Public Works office, said on Monday.
“Some streets have been repaired three times and are immediately damaged again because of the rain and puddles,” Ahmad said. “No matter how good the ‘hotmix’ is, it will not withstand the rain.”
The city should switch to higher quality concrete to prevent what has become an annual problem, he said in a statement that was echoed by the Indonesian Chamber of Commerce and Industry (Kadin) on Monday. The floods triggered during this year’s rainy season — and the damage they wrought on the drenched capital — have cost Jakarta up to Rp 300 billion ($24.6 million) per day in losses, according to Kadin deputy chairman Natsir Mansur.
Much of those losses are the result of the floods and damaged road network, which hindered shipping at North Jakarta’s Tanjung Priok Port. Scheduled shipments were delayed as trucks, struggling to traverse the capital’s flooded and potholed streets, failed to make it to the port in time.
Goods leaving the port were also delayed, causing additional losses, Natsir said.
“The buyers issued penalties on [distributors] because goods arrived behind schedule,” he said. “[And] we had to spend extra money to pay for the leftover cargo at the port. The letter of credit could not be disbursed.”
A concrete proposal
The use of more resilient concrete could shave 25 percent of maintenance costs off Jakarta’s annual budget, Natsir said. Nearly half of the roads in Jakarta suffered damages during this year’s rains, according to a Kadin survey. Using concrete instead of asphalt could prevent similar damages from occurring next year, he argued.
“Asphalt gets easily damaged, especially in conditions with high precipitation like Indonesia,” he said. “Roads covered with asphalt will be likely damaged in a year, while concrete lasts longer — approximately five years.”
A surge in the number of damaged roads illustrates the problems facing the city’s Public Works Department. Government data found that damage to the city’s roadways increased 133.6 percent in the last two weeks. Some 3,903 potholed locations are now in desperate need of repair — an increase of more than a 1,000 locations in less than a month.
The administration’s count likely under-estimates the problem, officials admitted. There are likely scores of smaller damaged roads that remained unreported on Monday.
One transportation expert said Jakarta’s efforts to address its inadequate road network were “woeful.”
Construction standards are sporadically enforced, said Soegeng Purnomo, of the Indonesian Transportation Society (MTI), in a previous interview with the Jakarta Globe.
“The quality of the roads in Jakarta are simply woeful,” Soegeng said. “And to make matters worse, the process of fixing them is just as bad.”
Workers rarely follow proper procedures when patching potholes, he argued. The substandard work is little more than a temporary fix for what quickly becomes a reoccurring problem.
“So you have a case where the mix of materials in the hot-mix isn’t even up to standard, and then it’s being poured at a much lower temperature than required, usually less than 100 degrees Celsius,” Soegeng said. “So obviously you end up with a stretch of road that will easily become potholed again.”
A deadly problem
The capital’s crumbling roads claimed 19 lives last year, a sad figure that will likely repeat itself this year if work fails to address the issue. Last month a seven-year-old boy was fatally run over by a truck after falling from his mother’s motorbike. The accident, police said, was caused by the boy’s mother hitting a pothole.
Three others died last month in accidents allegedly caused by the capital’s poor roadways, police said.
Deputy Governor Basuki Tjahaja Purnama said work would begin on roads leading to Tanjung Priok immediately. The city administration will prioritize work on 144,000 square meters of roadway — 3 percent of the capital’s total roads — located predominately in North Jakarta.
The administration plans to repave the roads with steel-reinforced concrete as soon as the rains let up, Basuki said. The concrete, which is theoretically more durable than the existing asphalt, is expected to last five years.
The deputy governor declined to specify the budget of the repairs, but said that it would be cheaper than the cost of annual roadwork — which had failed to adequately preserve the heavily traveled roads.
Source: jawawa.id (https://jawawa.id/newsitem/heavy-rain-takes-a-toll-on-jakartas-zero-pothole-plan-1392051600)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/news/jakarta/heavy-rain-takes-a-toll-on-jakartas-zero-pothole-plan/)