Govt Issues Order to Start Cikampek-Palimanan Toll Road Construction
JG & ID by Eko Adityo Nugroho
The Ministry of Public Works has issued official documentation ordering the start of the Cikampek-Palimanan toll road in West Java, Minister Djoko Kirmanto said on Friday.
The document, known as SPMK, “has been issued, and the investors have already thanked us,” Djoko said in Jakarta.
He said that with the document out, construction could begin immediately.
“Do not wait for days or even weeks, just work on it immediately,”
the minister said.
Under the existing plan, the 116.75-kilometer toll way should be partially operational by June 2014, with construction completed in 2.5 years.
The toll way is expected to require Rp 12.6 trillion ($1.3 billion) in investment. A syndication of banks, including BCA, Bank DKI, Bank Panin, Bank Jabar Banten and ICBC have already committed Rp 7.1 trillion.
Plus Expressways Berhad and Baskara Utama Sedaya respectively have stakes of 55 percent and 45 percent in Lintas Marga Sedaya, which will operate the toll road for 35 years.
The Cikampek-Palimanan toll road will be split into six sections — 29.1-kilometer Cikopo-Kalijati; 9.6-kilometer Kalijati-Subang; 31.4-kilometer Subang-Cikedung; 17.7-kilometer Cikedung-Kertajati; 14.5-kilometer Kertajati-Sumberjaya; and 14.5-kilometer Sumberjaya-Palimanan.
The toll road project had been delayed by land purchasing issues, with the bank syndication refusing to disburse the funds until all the land purchases had been finalized.
The Cikampek-Palimanan toll way had initially been scheduled for completion in 2011.