Geo Dipa Energi Secures Rp1.3 Trillion in State Capital Injection and Accelerates Two Geothermal Projects
State-owned geothermal energy developer PT Geo Dipa Energi (Persero) received Rp1.3 trillion in state capital injection from the national budget, allocated to geothermal sector development.
Geo Dipa Energi president director Yudistian Yunis said the funds were received in early 2019 as a prerequisite for financing the development of the Dieng Unit 2 and Patuha Unit 2 geothermal power plants.
The Patuha Unit 2 project is progressing, with commercial operation targeted for the first quarter of 2027. The unit is planned to have a capacity of 55 MW. Dieng Unit 2 is targeted to begin commercial operations in the first quarter of 2028.
Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/geo-dipa-energi-secures-rp1-3-trillion-in-state-capital-injection-and-accelerates-two-geothermal-projects-1792565447)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/market/20261021121855-19-778147/video-raih-pnm-rp-13-triliun-geo-dipa-energi-kebut-2-proyek-pltp), translated from Indonesian