Gedung Sate and Gasibu Revamp to Be Completed by 10 August 2026 for Independence Day Ceremony

| | Source: Media Indonesia Translated from Indonesian | Infrastructure
Gedung Sate and Gasibu Revamp to Be Completed by 10 August 2026 for Independence Day Ceremony
Image: Media Indonesia

The West Java Provincial Government is accelerating the completion of the iconic Gedung Sate area revitalisation project, which is being integrated with the Gasibu Field grounds in Bandung. This ambitious project is targeted for full completion by 10 August 2026, just ahead of the Republic of Indonesia’s Independence Day commemoration.

Based on on-site observations, the transformation of this West Java administrative centre has already shown significant changes. The courtyard area, which had previously been completely demolished down to ground level, has now largely been resurfaced. Expanses of green parkland and paving block arrangements are beginning to shape a new, more organised and integrated face for the precinct.

West Java Governor Dedi Mulyadi stressed that physical work on the ground is being pushed to meet the set deadline. While inspecting the site on Monday (3/8), he gave a brief but firm statement regarding the project’s completion schedule. “Finished by 10 August, 10 August,” said Dedi Mulyadi, confirming the area’s readiness for the upcoming state agenda.

Echoing the Governor, Head of the West Java Communication and Informatics Agency (Diskominfo), Adi Komar, explained that the revitalisation progress has now entered its final stage. The main focus is ensuring the Gedung Sate courtyard is ready to serve as the venue for the Independence Day ceremony. “As the Governor stated, the progress on the Gedung Sate courtyard is targeted for completion before 17 August and is still progressing. Physically, it is almost complete, just the finishing and final cleaning stages remain,” Adi Komar explained.

One public concern regarding the historic area’s renovation was the fate of the large trees that serve as the city’s lungs around Jalan Diponegoro. Responding to these concerns, Governor Dedi Mulyadi guaranteed that the integration project would not sacrifice the existing vegetation. Dedi confirmed that no large trees would be felled during construction. He noted that if any plants were affected, they would only be ornamental plants or very small trees that technically needed to be rearranged.

After the main construction phase is completed on 10 August, the area will be immediately prepared to host the 17 August ceremony. Adi Komar added that the use of the Gedung Sate courtyard as the centre for this year’s independence ceremony would be a significant moment following the extensive renovation. However, he noted that work would not stop entirely after the ceremony, with further construction planned for the northern part of the Gasibu area which is not required for the event.

More from 3 August 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/gedung-sate-and-gasibu-revamp-to-be-completed-by-10-august-2026-for-independence-day-ceremony-1785761469)
Originally published by Media Indonesia (https://mediaindonesia.com/nusantara/917798/penataan-gedung-sate-dan-gasibu-rampung-10-agustus-2026-untuk-upacara-hut-ri), translated from Indonesian
Print