From Pulubrayan Depot, KAI Prepares to Strengthen North Sumatra–Aceh Connectivity
Heavy maintenance of 129 rolling stock units and services for 1.39 million customers in the first half of 2026 are strengthening the readiness of railway operations in the northern part of Sumatra.
Medan (ANTARA) – PT Kereta Api Indonesia (Persero) continues to strengthen services already operating in Regional Division I of North Sumatra as well as the maintenance capacity of the Pulubrayan Workshop in Medan. This reinforcement is needed to maintain current services for the public whilst also preparing data and technical support for a study into developing rail connectivity between North Sumatra and Aceh.
The development of this connectivity still requires a comprehensive study and a government decision. The study must consider public travel demand, economic potential, safety, infrastructure readiness, operating patterns, spatial planning, environmental and social impacts, financing, and integration with the network already in operation.
KAI Vice President of Corporate Communication Anne Purba said the company is ready to support this process in accordance with the authority and assignments given by the government.
“North Sumatra–Aceh connectivity is still under study. KAI can provide support in the form of operational data, rolling stock requirements, service projections, and technical capabilities. While that process is under way, our priority is to ensure that the services already used by the public in North Sumatra remain safe and reliable,” Anne said.
Currently, the North Sumatra Regional Division I area has 476.460 kilometres of active track and 43 active stations spread across 13 regencies and cities. The network serves passenger travel and goods distribution to various areas, including Binjai, Tebing Tinggi, Pematangsiantar, Kisaran, Tanjungbalai, Rantauprapat, Belawan, Kuala Tanjung, and Kualanamu.
The existence of the active network provides initial data for reading travel patterns, centres of demand, operational requirements, and the potential for integration with ports, airports, industrial estates, plantation hubs, and regional economic centres.
Throughout the first half of 2026, KAI North Sumatra Regional Division I served 1,391,120 customers, growing by around 5 per cent compared with the first half of 2025, which totalled 1,328,372 customers.
By month, KAI served 233,133 customers in January, 200,042 in February, 265,081 in March, 221,254 in April, 235,824 in May, and 235,786 in June 2026.
Growth was evident on a number of main routes. The Sribilah Utama and Sribilah Fakultatif services on the Medan–Rantauprapat return route served 419,637 customers, up 8 per cent compared with 387,459 customers in the first half of 2025.
The Putri Deli service on the Medan–Tanjungbalai return route served 649,892 customers, growing 2 per cent compared with 639,839 customers. Meanwhile, the Siantar Ekspres on the Medan–Pematangsiantar return route served 272,759 customers, an increase of 9 per cent compared with 251,088 customers.
These three services accounted for around 96.5 per cent of the total customers of North Sumatra Regional Division I in the first half of 2026. The data demonstrates the strong demand for travel between Medan and the centres of activity on the eastern side of North Sumatra.
“Customer growth is important data for planning capacity and service patterns. Every network development plan must be drawn up based on public needs, operational feasibility, and the economic and social benefits it can generate,” Anne said.
Operational readiness in North Sumatra is supported by the Pulubrayan Workshop, which has performed rolling stock maintenance functions since 1915. For more than a century, this facility has handled the heavy maintenance of locomotives, passenger carriages, generator cars, freight wagons, and special equipment.
In the first half of 2026, the Pulubrayan Workshop completed heavy maintenance on five locomotives, 18 passenger carriages, 102 freight wagons, three generator cars, and one piece of special equipment. The total of 129 rolling stock units represents 100 per cent of the first-half 2026 maintenance programme.
Maintenance is carried out on 24-month, 36-month, 48-month, and up to 72-month cycles depending on the type and technical requirements of each unit. The work includes inspection and repair of engines, structures, braking systems, wheelsets, bogies, electrics, interiors, and functional testing before the rolling stock returns to service.
The Pulubrayan Workshop is also converting two decommissioned former carriages into relief trains. The work includes structural modifications, electrical installation, partitions, ceilings, ventilation, and supporting equipment to help handle emergencies on the line.
“The Pulubrayan Workshop maintains the availability of rolling stock for passenger and goods services in North Sumatra. This maintenance capacity needs to be maintained and developed gradually in line with operational needs and the direction of government policy,” Anne said.
The reliability of the rolling stock also supported services during the school holidays. In the period 20 June to 5 July 2026, rail services in the North Sumatra Regional Division I area recorded 141,799 customers. Of that total, Medan Station served 49,403 departing customers and 51,374 arriving customers.
For the 30 per cent transport discount programme in North Sumatra, the promotion was offered on the Sribilah Fakultatif service on the Medan–Rantauprapat return route. During the school holiday period, the Sribilah Fakultatif served 9,044 customers, and all customers on that service received the 30 per cent discount.
“The uptake of the Sribilah Fakultatif promotion demonstrates the strong travel demand between Medan and Rantauprapat. Service programmes like this must still be supported by the readiness of rolling stock, staff, stations, and good traffic management,” Anne said.
Nationally, the transport discount programme during the school holidays was used by 1,303,191 customers, an increase of around 11 per cent compared with the 2025 programme period, which totalled 1,173,612 customers. Total KAI services in the period 20 June to 5 July 2026 reached 3,451,031 customers, growing by around 4 per cent compared with the previous period.
KAI will continue to coordinate with the Ministry of Transport, regional governments, and relevant stakeholders in providing data and technical input for the North Sumatra–Aceh connectivity study. No construction decision or operating schedule has yet been made, as all stages still depend on the results of the study and government policy.
“KAI is maintaining reliable services in North Sumatra whilst also preparing its technical capabilities to support government policy. If the study results point towards developing connectivity to Aceh, KAI is ready to carry out its role in accordance with the authority and assignments given,” Anne concluded.
Source: jawawa.id (https://jawawa.id/newsitem/from-pulubrayan-depot-kai-prepares-to-strengthen-north-sumatra-aceh-connectivity-1783673795)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5644067/dari-balai-yasa-pulubrayan-kai-siap-perkuat-konektivitas-sumut-aceh), translated from Indonesian