Freeport Underground Mine Production to Fully Recover by End of 2027

| Source: CNBC Indonesia Translated from Indonesian | Mining
Freeport Underground Mine Production to Fully Recover by End of 2027
Image: CNBC Indonesia

PT Freeport Indonesia (PTFI) is targeting its underground mine production to reach 100% of normal output by the end of 2027, following the recovery of operations at the Grasberg Block Cave (GBC) which was hit by a wet mudslide incident in September 2025.

President Director of PTFI Tony Wenas said that by the end of 2026, the company is targeting production at 65% of normal levels. The company is currently working hard to modify equipment to accelerate operational normalisation in the GBC area.

“Going forward, production capacity is expected to increase to 75% in the first half of 2027 and gradually approach full capacity by the end of 2027,” he said in a speech at the 81st Independence Day ceremony in Tembagapura, Central Papua, quoted on Tuesday (18/8/2026).

By the end of the second half of 2026, PTFI is targeting production capacity of 800 million pounds of copper and 700,000 ounces of gold.

According to Wenas, the GBC mine recovery process is quite challenging because the company must remove around 800,000 tonnes of wet mud material that buried a number of infrastructure and heavy equipment in the underground mine area.

“This recovery phase continues, and there have been some equipment modifications because the ore turned out to be wetter than we previously estimated. So the equipment needed to be modified slightly, but it is now ongoing, all in line with the 65% target this year,” he said on the sidelines of the event.

Nevertheless, the company still projects it can contribute Rp 47 trillion to the state this year.

“And when we are at 100%, the contribution to the state could be extraordinarily large, more than Rp 100 trillion, perhaps Rp 120 trillion every year. So that is roughly Freeport’s contribution to the state,” he concluded.

More from 18 August 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/freeport-underground-mine-production-to-fully-recover-by-end-of-2027-1787032348)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20260818112648-4-760241/produksi-tambang-bawah-tanah-freeport-pulih-100-di-akhir-2027), translated from Indonesian
Print