Freeport to Invest Rp 72 Trillion in Kucing Liar Mine
PT Freeport Indonesia (PTFI) has revealed that it has invested approximately Rp 25 trillion to develop a new underground mine, known as Kucing Liar, located in the Grasberg Mineral District, Central Papua. By 2033, this project is projected to require a total investment of around Rp 72 trillion. The project is being prepared as a long-term initiative to ensure the company’s operational stability.
President Director of PT Freeport Indonesia, Tony Wenas, stated that the development of the Kucing Liar mine has now entered the development stage. Production from the mine is targeted to begin in 2029.
“I also wish to inform here that the Kucing Liar mine, which is our mine of the future, is being worked on starting now; it has entered the development stage and will be ready for mining in 2029,” said Tony during a hearing with Commission XII of the Indonesian House of Representatives (DPR RI), as reported on Tuesday (22/09/2026).
Tony revealed that, to date, the company has spent approximately Rp 25 trillion on the development of the Kucing Liar mine. This investment figure is part of the total projected investment requirement of approximately Rp 72 trillion through to 2033.
“We have spent about Rp 25 trillion on the development of this Kucing Liar mine out of a total of Rp 72 trillion up to 2033,” he added.
As previously reported, based on Freeport-McMoRan (FCX) reports, PT Freeport Indonesia has been conducting long-term mine development activities at the Kucing Liar deposit in the Grasberg mineral district since 2022.
In 2025, the company completed a study to evaluate the potential for expanding the deposit footprint, which was originally designed to operate at a capacity of 90,000 metric tonnes of ore per day.
The study identified low-cost expansion opportunities to increase capacity to 130,000 metric tonnes per day, while simultaneously increasing reserves by approximately 20%.
“As of 31 December 2025, PTFI’s initial estimates for the Kucing Liar reserves are close to 8 billion pounds of copper and 8 million ounces of gold to be recovered until 2041, an increase from previous estimates of 7 billion pounds of copper and 6 million ounces of gold,” the management wrote in a statement on Monday (26/01/2026).
Based on the latest design, average production at Kucing Liar at full capacity will reach approximately 750 million pounds of copper and 735,000 ounces of gold, an increase of more than 35% from previous estimates.
According to the company’s economic study, the development of Kucing Liar requires an additional capital investment of approximately 10%, or US$0.5 billion, including the impact on the operations of the Grasberg Block Cave and adjustments to processing facilities.
Source: jawawa.id (https://jawawa.id/newsitem/freeport-to-invest-rp-72-trillion-in-kucing-liar-mine-1790049278)