Freeport Targets Gresik Smelter to Resume Operations in September 2026

| Source: CNBC Indonesia Translated from Indonesian | Mining
Freeport Targets Gresik Smelter to Resume Operations in September 2026
Image: CNBC Indonesia

PT Freeport Indonesia says its new copper processing and refining facility (smelter) at the Java Integrated Industrial and Port Estate (JIIPE) in Gresik, East Java, will resume operations in September 2026.

PTFI President Director Tony Wenas said that after the landslide at the Grasberg Block Caving underground mine in Tembagapura, Mimika Regency, Central Papua, on 8 September 2025, the company’s second smelter had been idle since October 2025.

The smelter received no copper concentrate supply from the underground mine because mining operations were suspended following the landslide incident.

“Production indeed halted around October 2025, because on 8 September there was a landslide at Grasberg Block Caving which cut off the concentrate supply, so the smelter was only processing or refining the remaining concentrate in the warehouse, and since December it stopped completely,” he explained during a hearing with Commission XII of the Indonesian House of Representatives on Tuesday (14 July 2026).

“But on the other hand, the total shutdown enabled us to carry out maintenance and repairs to ensure that when the new smelter resumes production after receiving concentrate again from upstream in Papua, all processes have been checked and it can operate again,” he said.

“The plan is for the new smelter to start producing again, processing and refining concentrate from Papua, in September this year, with a ramp-up until the end of the year,” he added.

Meanwhile, PTFI’s first copper smelter, operated under PT Smelting, is still running, processing nearly 50% of the concentrate from Freeport’s underground mine in Papua.

Tony said the production capacity of Freeport’s underground mine in Papua is still around 60%, not yet fully normal as before the landslide incident.

This year, the mine’s production capacity is expected to reach only 65% of total capacity, then gradually rise to 75% in the first half of 2027, and is expected to return to 100% capacity by the end of 2027.

“As is known, this year PTFI is still at only 60% capacity upstream because of the September landslide — we are carrying out repairs to make sure everything is truly safe, so the production ramp-up is not running as we previously estimated. This year it will still reach 65% of total capacity. The first semester of next year will reach 75% of capacity, and by the end of 2027 it will head towards 100% capacity,” he explained.

It is worth noting that before halting in October 2025, the second Freeport smelter had actually begun operating in June 2024, though still in the commissioning phase. It then started production in August 2024.

However, in October 2024 a fire broke out in the smelter area, in one small unit, the gas cleaning plant, which captures SO2 from the furnace so that the SO2 is not released into the air and is instead processed into sulphuric acid. Repairs were carried out and the smelter was able to operate again in May 2025.

The smelter project, valued at US$4.2 billion, processes 1.7 million tonnes of copper concentrate per year and also increases processing capacity at the PT Smelting facility by 0.3 million tonnes, to 1.3 million tonnes of copper concentrate per year.

The second smelter project at JIIPE Gresik produces 600,000 tonnes of copper cathode and precious metal refinery (PMR) products of 6,000 tonnes per year, or around 50 tonnes of gold per year.

More from 14 July 2026 →

Cite this article