Freeport Targets Full Production Recovery by End of 2027
JAKARTA – The President Director of PT Freeport Indonesia (PTFI), Tony Wenas, said the company’s production will recover gradually after being hit by a landslide at the Grasberg Block Cave (GBC) underground mine. PTFI is targeting production capacity to return to 100 percent by the end of 2027.
The recovery is being carried out alongside repairs to the mine area and the resumption of concentrate supplies to the smelter in Gresik. The new smelter is scheduled to begin processing concentrate from Papua again in September 2026, followed by a ramp-up process until the end of the year.
“This year we will still reach 65 percent of total capacity. In the first half of next year we will reach 75 percent of capacity, and towards the end of 2027 we will reach 100 percent capacity,” Tony said during a hearing with Commission XII of the House of Representatives (DPR RI) at the Parliamentary Complex in Senayan, Jakarta, on Tuesday (14/7/2026).
He explained that the landslide, which occurred on 8 September 2025 at Grasberg Block Cave, had stopped the supply of concentrate to the smelter. The condition meant the refining facility only processed the remaining concentrate available in storage before it finally ceased operations in December 2025.
PTFI used the operational halt to carry out maintenance and improvements across the entire smelter facility. The step was taken so that all systems would be ready to resume operations once concentrate supplies from Papua returned to normal.
“The new smelter plan is to begin processing and refining concentrate from Papua in September this year, then undergo a ramp-up process until the end of the year,” Tony said.
Currently, PT Smelting continues to operate and processes roughly half of the concentrate produced by PTFI in Papua. On the upstream side, mine production this year is estimated to reach around 124,000 tonnes of ore per day, lower than last year’s realisation of 139,000 tonnes per day.
In 2026, PTFI is targeting production of around 800 million pounds of copper and 700,000 ounces of gold, equivalent to about 21 tonnes of gold. Production is projected to rise to 1.2 billion pounds of copper and 1 million ounces of gold, or around 31 tonnes, in 2027.
Production capacity is set to increase further in 2028 to around 1.6 billion pounds of copper and 1.4 million ounces of gold, or approximately 43 tonnes. Ore production is also expected to rise to 208,000 tonnes per day before reaching around 226,000 tonnes per day in 2029.
“In 2029, the mine we are currently developing, the Kucing Liar mine, is planned to begin operations. This mine is being prepared to replace DMLZ, which has begun to see a decline in tonnage,” Tony said.
The Kucing Liar mine is being prepared to ensure production continuity after DMLZ enters its declining phase. With the development of the new mine, PTFI is targeting a production level of around 220,000 tonnes of ore per day that can be sustained in the long term.
Source: jawawa.id (https://jawawa.id/newsitem/freeport-targets-full-production-recovery-by-end-of-2027-1784019207)