Freeport Indonesia's Copper Ore Production to Remain at 65% in 2026 Due to Landslide
Jakarta, CNBC Indonesia – PT Freeport Indonesia (PTFI) projects its mining production capacity will reach only 65% in 2026, following the landslide incident at the Grasberg Block Cave (GBC) underground mine in September 2025.
PTFI President Director Tony Wenas explained that the company is still focusing on the operational recovery phase following last year’s incident at GBC. He stressed that the company prioritises safety at the mining area, ensuring it is truly secure before pushing for increased production.
“As is known, this year we at PTFI are still only at 60% of upstream capacity because, as a result of the landslide in September (2025), we have been carrying out repairs and making certain that everything is truly safe, so the production ramp-up has not proceeded as we previously estimated. This year we will still only reach 65% of total capacity,” he said during a hearing with Commission XII of the House of Representatives (DPR RI) in Jakarta on Tuesday (14 July 2026).
Daily copper ore mining volumes have also declined, with the 2026 target set at 124,000 tonnes — down from the 2025 realisation of 139,000 tonnes of ore per day before operations were halted.
“In 2026, the amount of metal we will produce is roughly 800 million pounds of copper and 700,000 ounces of gold, or the equivalent of about 21 tonnes,” he explained.
The company is targeting a gradual increase in production capacity to return to normal levels above 200,000 tonnes of ore per day.
In the first half of 2027, mining production capacity is planned to rise to 75%, with full recovery to 100% projected only by the end of 2027.
“In 2027 we could reach 1.2 billion pounds of copper and one million ounces of gold, or around 31 tonnes. And in 2028 there will be a further increase to 1.6 billion pounds of copper and 1.4 million ounces of gold, or 43 tonnes of gold, and so on until 2030,” he added.
In addition, PTFI is preparing the development of a new mine, the Kucing Liar block, which is scheduled to begin production in 2029. This is being prepared to replace the Deep Mill Level Zone (DMLC) block, whose volume is predicted to decline in the future.
“This is to replace DMLC, whose tonnage is starting to fall, so that the stability or continuity of mining at around 220,000 tonnes of ore per day can be maintained,” he concluded.
Source: jawawa.id (https://jawawa.id/newsitem/freeport-indonesias-copper-ore-production-to-remain-at-65-in-2026-due-to-landslide-1784019104)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20260714134416-4-750701/imbas-longsor-produksi-bijih-tembaga-freeport-masih-65-di-2026), translated from Indonesian