JAKARTA - Copper concentrate output at Freeport-McMoRan Inc's Indonesian mine will fall almost 20 percent this year following a seven-month tax row that halted exports, the company's local chief executive said on Wednesday.

Arizona-based Freeport has also built up a near capacity 140,000 tonne stockpile, despite reducing production in recent months and maintaining shipments to its part-owned Gresik smelter in East Java, Freeport Indonesia CEO Rozik Soetjipto told Reuters.

Exports resumed earlier this month after the mining giant, which runs one of the world's biggest copper mines in Papua, clinched a deal with the Indonesian government in July to end a dispute over a controversial tax on metal concentrates.

Total copper concentrate production will reach 1.8 million tonnes this year, down from an expected 2.2 million tonnes, with exports of about 700,000 tonnes, Soetjipto said.

"Already this year we have one shipment to China, and maybe in the coming few days another to Spain," he said. He could not give an exact timetable for running down the 140,000 tonne inventory, which was just 5,000 tonnes below capacity.

"Every day we add roughly 5,000-6,000 tonnes when operations are normal," Soetjipto added.

The export tax introduced in January was part of moves by Indonesia to force miners to develop local mineral processing facilities, which would bring bigger returns for the government from the country's vast mineral resources.

The industry has generally balked at the idea of developing downstream industries and building smelters, citing a lack of power and infrastructure in remote areas where mines are often located.

Agreement to resume exports was reached after Freeport signed a memorandum of understanding with the government, covering aspects such as royalty payments, the export tax, smelter construction, and divesting an extra 20 percent stake in the Indonesian unit. The government already has a 9.36 percent stake in Freeport Indonesia.

SMELTER OPTIONS

Freeport currently smelts about 40 percent of its output from Grasberg at Indonesia's only copper smelter in Gresik, East Java.

Soetjipto said the firm was currently reviewing four possible locations in East Java for a new smelter, which would cost about $2.3 billion to build and have an annual production capacity of about 400,000 tonnes.

The smelter would be designed only to take concentrate from Freeport's mines, but the company had not yet lined up funding or reached any agreement on who would build the plant.

The memorandum of understanding allowed exports to resume, restoring revenue to the government and ensuring the mine remained open, but is not seen by experts as legally binding.

Freeport will need to deal with a new administration from October after last month's elections, as it negotiates to continuing mining past 2021 when its current contract expires.

Soetjipto, who was previously a senior official in the mines ministry, said there was no definitive agreement on how Freeport Indonesia would make its additional divestment.

"My understanding is roughly within five years - that is when the government would like us to finalise that," he said.

Freeport Indonesia would continue to invest the billions of dollars needed to turn Grasberg into an underground mine after 2016, as talks continued on a new mine licence.

"We try as much as possible to keep our schedule for the development of underground - there is of course some delay but hopefully it is not that significant."

Government officials say Freeport can only extend their current 2021 contract of work in 2019 at the earliest.

(Editing by Richard Pullin)

More from 14 August 2014 โ†’

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/freeport-indonesia-sees-2014-output-down-20-pct-after-tax-row-1407949200)
Originally published by Reuters (http://www.ubs.wallst.com/ubs/mkt_story.asp?docKey=1329-L4N0QJ373-1&first=0)
Print