Indonesian Political, Business & Finance News

Freeport Copper Production to Fully Recover by End of 2027 After Landslide

| Source: CNBC Indonesia Translated from Indonesian | Mining
Freeport Copper Production to Fully Recover by End of 2027 After Landslide
Image: CNBC Indonesia

PT Freeport Indonesia (PTFI) is targeting a full recovery of underground mining capacity at the Grasberg Block Cave (GBC) in Papua to 100% by the end of 2027, following efforts to repair and maintain infrastructure after the material collapse incident in September 2025.

PTFI President Director Tony Wenas explained that the company is currently carrying out a phased production ramp-up to ensure safety aspects. He stressed that the company’s current focus is to make certain that all underground mining areas are genuinely safe before returning to normal production levels.

“This year we will still reach 65% of total capacity. The first half of next year will reach 75% of capacity, and towards the end of 2027 we will move towards 100% capacity,” he said during a hearing with Commission XII of the Indonesian House of Representatives (DPR RI) in Jakarta on Tuesday (14/7/2026).

The company recorded that ore mining volume in 2026 is planned at only 124,000 tonnes per day, down from last year’s realisation of 139,000 tonnes per day. The reduced production capacity is a direct consequence of the GBC landslide, which hampered concentrate supplies to the company’s smelter.

“As a result of the landslide that occurred in September, we have been carrying out repairs to make certain that everything is truly safe, so the production ramp-up has not progressed quite as we previously estimated,” he added.

The company is targeting daily ore mining volume to increase from 2027, with an average target of 170,000 tonnes, then rising to 208,000 tonnes in 2028 and reaching 226,000 tonnes per day in 2029. The increase in ore volume will significantly boost copper and gold metal production.

“In 2027 we can reach 1.2 billion pounds of copper and one million ounces of gold, or around 31 tonnes. And in 2028 there will be a further increase to 1.6 billion pounds of copper and 1.4 million ounces of gold, or 43 tonnes of gold, and so on until 2030,” he explained.

The processing sector is also preparing to resume full operations in September 2026 to refine ore supplies from Papua, having been halted since the end of last year. In addition, Freeport is preparing a new mine at the Kucing Liar Block, scheduled to begin production in 2029 to maintain supply stability as output from existing mining blocks begins to decline naturally.

“The new smelter is planned to resume production, or process and refine concentrate from Papua, in September this year, and will undergo a ramp-up until the end of the year,” he concluded.

More from 14 July 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/freeport-copper-production-to-fully-recover-by-end-of-2027-after-landslide-1784019133)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20260714134926-4-750702/imbas-longsor-produksi-tembaga-freeport-bakal-pulih-100-akhir-2026), translated from Indonesian
Print