North Sumatra’s new Kuala Namu International Airport will start commercial operations this week, marking some progress in the development of infrastructure that has in recent times struggled to keep pace with economic growth.
The Transportation Ministry said on Monday that Kuala Namu airport will handle domestic and international flights from Thursday, 18 years after the airport serving Medan was first planned under the administration of former president Suharto.
Construction on the airport, operated by state-controlled airport operator Angkasa Pura II, did not begin until 2007. “There was no budget allocation for construction of Kuala Namu for several years,” said Bambang S. Ervan, a ministry spokesman.
“We actually got the allocation immediately after the airport was planned but it was then cancelled in 1997 due to the financial crisis. The government had other priorities,” he added, referring to the crippled economy and sectarian disturbances that spread across Indonesia in the late 1990s.
But now Kuala Namu airport, which will take the international letter code KNO, is ready to welcome its first commercial flight after completing the Rp 5.5 trillion ($537 million) construction project.
Medan’s Polonia Airport, which will be replaced by Kuala Namu, is massively overcrowded. Last year, 6.9 million passengers used 900,000-capacity airport.
Polonia airport is located in a populated area with no room for expansion, so the government had little option but to build a new one elsewhere.
Planning ahead
Djoko Murjatmodjo, the director for air traffic at the ministry, said Kuala Namu would be at full capacity of 8.1 million passengers annually within five years, according to current projections, adding that further expansion of the airport is already being planned.
Bambang said the government planned to add another runway to the airport.
The airport will be served by Indonesia’s first-ever airport rail service. Railink, a subsidiary of state rain operator Kereta Api Indonesia, said the train service is ready to operate on Thursday in time for the first flight.
The rail link is expected to accommodate at least 20 percent of the estimated 21,000 passengers passing through the airport daily, Bambang said.
But other ground transportation links are proving troubling.
Bambang conceded passenger access to Kuala Namu is not yet up to the standard expected of an international transportation hub. “We urge passengers to go to the airport early,” he added.
As well as the railway, three standard roads and a toll road will lead to the new airport.
A road and the toll road, both directly connecting Medan to the airport, are not yet complete due to land acquisition problems, Public Works Minister Djoko Kirmanto said last week.
The ministry is responsible for building the road but the time-consuming process of acquisition is the regional government’s responsibility.
The current state of the road means a journey from the center of Medan to the airport, a distance of 32 kilometers, can take up to two hours.
National airline Garuda Indonesia on Monday reminded its customers to arrive at least two hours before departure.
Garuda’s GA 181 flight to Jakarta will be its first to fly out from Kuala Namu at 5 a.m. on Thursday.
The road to the airport will be ready in September, according to unconfirmed media reports, while the toll road is unlikely to be completed until 2015.
Slew of projects
The new airport is one of several big transportation infrastructure projects underway in Indonesia.
Ngurah Rai International Airport in Bali is currently being overhauled. When it is finished it will have an annual capacity of 40 million passengers.
Other major hubs such as Adisucipto in Yogyakarta and Surabaya’s Juanda have experienced growth in passenger numbers and been expanded over recent years.
Airport operator Angkasa Pura II is reported to be pumping Rp 11.7 trillion into a massive makeover that will expand the capacity of Soekarno-Hatta International Airport, which services Jakarta, to 62 million passengers a year, turning it into a world-class facility.
The airport handled 57 million passengers in 2012. It was the third busiest airport in Asia in 2012 according to Airport Council International, a trade organization of airports, while Jakarta-to-Surabaya was the 15th busiest route in the world in 2010 according to the Center for Aviation.
Source: jawawa.id (https://jawawa.id/newsitem/first-planned-in-suhartos-era-medans-new-airport-is-ready-1374512400)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/business/first-planned-in-suhartos-era-medans-new-airport-is-ready/)