Facts Behind the Emergency Bridge in Sumatra's Disaster Zone, Revealed in an Open Letter from Simalungun Residents

| Source: Tempo (Indonesian) Translated from Indonesian | Infrastructure

INFO TEMPO – An open letter from residents of Simalungun Regency, North Sumatra, recently circulated on social media feeds. The issue is that the connecting road between Nagori Marubun Lokkung in Dolok Silau District and Tinggi Raja in Silou Kahean District was severed by floods and landslides in November 2025.

The severed road has disrupted access. Children have struggled to travel to and from school, along with other mobility needs. In the end, the community built an emergency bridge on a self-help basis from tree trunks and planks. However, the river current damaged the bridge again, forcing residents to rebuild it.

The situation was then conveyed through an open letter uploaded to social media by a resident, Dita Purba, at the end of June 2026. The post attracted public attention.

The Simalungun Regency Government immediately went to the site and explained that it was accelerating the completion of a permanent bridge.

Why has the construction of the permanent bridge appeared to take so long? To understand the issue, one must look at the sequence of events since the disaster occurred. Investigations show that construction actually began long before the residents’ open letter circulated.

Based on a review by the Rehabilitation and Reconstruction Acceleration Task Force (Satgas PRR), construction of the permanent bridge began after the landslide disaster that occurred at the end of December 2025.

The Simalungun Regency Government established the construction of the permanent bridge through a work contract numbered SP-P04/PPK-BTT/XII/29.4/2025, issued on 24 December 2025, with a budget of around Rp 4 billion.

Physical work then began in early January 2026 with a target completion period of 180 days, or until 20 June 2026. “However, during implementation, field conditions changed. High rainfall triggered several subsequent landslides around the project site, so the work could not proceed according to the original plan,” wrote Kaposko Inspector General of Police Wahyu Bintono in his report to Task Force Chief Tito Karnavian, received by Tempo on Thursday, 9 July 2026.

The subsequent landslides necessitated design adjustments as well as an increase in work volume to make the bridge construction safer. The length of the retaining wall (TPT), for instance, increased from the original 30 metres to 39 metres. Meanwhile, the box culvert work rose from 9 metres to 21 metres.

The project’s implementation also faced material distribution constraints due to limited transport access to the site. Some materials even had to be brought in from outside the area because supplies near the location were insufficient.

On the other hand, the limited working space posed its own challenge. The route continued to be used by the community for daily activities, including as the main access for transporting agricultural and plantation produce. This situation meant the work had to be adjusted so that residents’ mobility could continue.

Based on field evaluations, the Simalungun Regency Government plans to extend the implementation period of the work until August 2026 as a consequence of changing field conditions and the increased volume of work.

The regency government will also improve communication with the community regarding work progress, including through the installation of project information boards at the site.

Satgas PRR continues to monitor and evaluate the bridge construction in Marubun Lokkung alongside a number of other infrastructure projects still facing obstacles in the North Sumatra region.

Satgas PRR Media Coordinator, Kastorius Sinaga, said the National Post Team of Satgas PRR, together with the Directorate General of Regional Finance Development at the Ministry of Home Affairs, is scheduled to visit North Sumatra on 13–16 July 2026.

“The Satgas PRR National Post Team, together with the Directorate General of Regional Finance, will make a visit to North Sumatra Province, including Simalungun Regency. In addition to discussing the completion of the bridge reconstruction, the team will also facilitate the use of Additional Transfer Funds (TKD) to improve regional preparedness in accordance with the Minister of Home Affairs’ circular letter,” said Kastorius.

More from 9 July 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/facts-behind-the-emergency-bridge-in-sumatras-disaster-zone-revealed-in-an-open-letter-from-simalungun-1783591022)
Originally published by Tempo (Indonesian) (https://nasional.tempo.co/read/2112772/fakta-kondisi-jembatan-darurat-bencana-sumatera-yang-dimuat-dalam-surat-terbuka-warga-simalungun), translated from Indonesian
Print