Indonesian Political, Business & Finance News

Experts uncover more than 4,000 artefacts during Jakarta MRT Phase 2A project

| Source: Antara (Indonesian) Translated from Indonesian | Infrastructure
Experts uncover more than 4,000 artefacts during Jakarta MRT Phase 2A project
Image: Antara (Indonesian)

Jakarta (ANTARA) – The archaeological expert team working on the Jakarta MRT Phase 2A project has uncovered more than 4,000 artefacts and historical remains during construction of the Bundaran Hotel Indonesia–Kota line. The finds include ceramics from several countries that illustrate historical trade relations.

“The number increases every day. Each time we remove a new stake or a new plank from the canal, the data grows. I don’t know the latest figure, but if we’re talking about more than 4,000, then certainly it’s higher,” said Junus Satria Atmodjo, an archaeological adviser to the Jakarta MRT Phase 2A project and a member of the National Cultural Heritage Expert Team. He was speaking after the handover of archaeological finds from the project at Jakarta Kota station in Jakarta on Thursday.

Junus said the number of discoveries continued to rise as construction progressed. They include terracotta water-channel structures, stakes associated with river walls and loose artefacts such as ceramics.

He said the ceramics point to trade links between Indonesia and other countries, including Japan, China, Vietnam, Thailand and Cambodia.

Around 200 objects were previously taken to Japan for an exhibition at the Indonesian Embassy in Tokyo. Although the collection was limited, it attracted considerable interest from local visitors.

Junus added that archaeological finds could help people understand Indonesia’s history through material evidence, while showing that the Indonesian archipelago had been connected to international trading networks since ancient times.

Indra Gunawan, MRT Jakarta’s Project Management for Construction 2 representative, said the finds would be curated before being put on public display.

A gallery planned for Jakarta Kota station will introduce the historical discoveries to MRT passengers and the wider public.

Construction of Jakarta MRT Phase 2A was 65.10 per cent complete as of 25 September 2026. The Bundaran HI–Harmoni section is due to be completed in 2027, followed by the Harmoni–Kota section in 2029.

More from 15 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/experts-uncover-more-than-4-000-artefacts-during-jakarta-mrt-phase-2a-project-1792065278)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5788841/tim-ahli-temukan-lebih-4000-artefak-dari-proyek-mrt-jakarta-fase-2a), translated from Indonesian
Print