Environmental Impact Assessment for Lembar-Kayangan Bypass Project Targeted for Completion by December 2026
The plan to construct the Lembar-Kayangan Bypass in West Nusa Tenggara (NTB) has now entered the stage of preparing environmental impact assessment (Amdal) documents. The Amdal documents are targeted for completion by December 2026.
“This is so that by 2027, the documents are ready, the Detailed Engineering Design (DED) is ready, and the Amdal is ready. Other necessary elements will also be prepared,” stated the Head of the West Nusa Tenggara Public Works and Spatial Planning Department (PUPR), Lalu Kusuma Wijaya, during a public consultation for the Amdal in East Lombok on Wednesday (7/10/2026).
Lalu Wijaya explained that the preparation of the Amdal must involve socialisation and public consultation. Through this stage, the community is provided with an understanding regarding the potential impacts of the road project.
“This is to ensure the community is not confused, so socialisation is conducted early. This way, the project will not appear to be a sudden activity carried out without prior notice,” he added.
The public consultation for the segment spanning Central Lombok to Kayangan, East Lombok, involves representatives from 28 affected villages, particularly those in the southern region of East Lombok that the bypass will traverse.
“The route originates from the southern region of East Lombok, so we have invited representatives from villages in the south. Most of the existing roads are located in the southern part,” he explained.
Lalu Wijaya noted that the bypass construction project requires a lengthy process. Once the Amdal documentation is completed, the next stage will be land acquisition.
“The land acquisition process is still long, but the scenario is that by 2029, God willing, the roads will be connected, even if the project is not yet fully completed,” he concluded.