Electricity In Indonesia Needs Not Just Funding But Land and Licences

| Source: The Establishment Post

The Establishment Post By Dewi Kurniawati

President Jokowi’s first overseas trip to China recently to attend the Asia-Pacific Economic Cooperation (Apec) in Beijing brought two issues to the fore. First was his speech in front of hundreds of business people attending the prestigious Apec Chief Executive Officer (CEO) summit. Second, he proposed to President Xi Jinping that the China-led Asian Infrastructure Investment Bank (AIIB) open its headquarters in Jakarta.

In his 13-minute presentation in front of the Apec CEO summit in Beijing, President Jokowi laid out his ambitious infrastructure project plans and pledged to allocate most of his resources in the immediate term to facilitate their construction, with one crucial goal: to boost Indonesia electricity production and distribution.

His goals as laid out in his power point slides during his talk included the construction and expansion of 24 integrated seaports across the archipelago, the development of toll roads along the shore of Java, as well as the construction of 35,000 megawatt power plants.

“This is your opportunity to invest in Indonesia,” Mr Joko Widodo repeatedly told the Apec CEO summit, while at the same time admitting the country’s limited budget which made it difficult to build infrastructure for the vast archipelago country to sustain its economic growth.

Poor infrastructure is often cited as the main factor preventing Indonesia’s economy from growing at its potential rate of eight per cent. Inadequate infrastructure also results in a higher cost structure compared with most of Indonesia’s peers in Southeast Asia.

The government has introduced a public-private partnership (PPP) plan aimed at attracting private investors in infrastructure investment, but private investors will have to depend on offshore or foreign financing due to the limited capacity of domestic banks to finance infrastructure projects.

Reports said, Jokowi’s visit to China successfully secured investment in various sectors worth more than US$ 20 billion.

35,000 MegaWatt Power Plants Need Land

President Jokowi’s ambitious plan to provide 35,000 megawatt power plants in the next five years is a huge challenge to achieved for Nur Pamudji, president director of the state-owned electricity company (PT PLN or Perusahaan Listrik Negara ), as it was the first thing he mentioned when addressing a panel on electricity in Indonesia in Jakarta recently.

“The plan will require hard work and huge budget spending, but it must be done because first we need that to support the goal of six per cent economic growth, while second is to provide services for the country’s remote areas,” Mr Pamudji said.

Surprisingly, although budget plays an important role in improving supply of electricity in Indonesia, it is not the most challenging issue faced by the state-owned company. “It is land acquisition, getting the permit, and finding good contractors,” he said with constant smile on his face.

On the land acquisition problem for example, Nur Pamudji highlighted the case of the nation’s first and largest public-private partnership project, the 2,000 megawatt Batang coal-fired power plant in Central Java province which requires an area of around 226 hectares and has faced years of delay.

According to its original plan, the Batang power plant will begin construction in 2012 and was slated for commercial operation by the end of 2016. However under the current condition, the power plant may commence commercial operation by 2019 at the earliest.

The Land Acquisition Act Upheld by the Constitutional Court

“There are only few people, probably less than 15 people, still not willing to sell their land for this power plant,” Mr. Pamudji told the panel, hoping that local government officials in central Java will use the “Jokowi approach” of lunching and munching with local residents to sway their hearts and break the deadlock on land acquisition needed for the power plant operation.

If moral suasion fails, the central government can intervenes using the 2011 land acquisition law, which is seen as crucial to removing hurdles that have long impeded key infrastructure projects in Indonesia. Under the law, all legal proceedings pertinent to land acquisition for a government-commissioned infrastructure project should be completed within 436 working days at the most.

The Constitutional Court in 2013 decided to upheld the land acquisition law after several society groups claimed it violates the constitution or the rights of the public and filed for a judicial review. The plaintiffs requested that the court annul nine articles of the law they said that would allow the government to seize people’s land if it was in the public interest.

“We need 140 new plant sites within the next five years, and each plant needs between 50 to 200 hectares area,” Mr Pamudji said.

The Long Road to a Licence

Another headache faced by the electric company to provide enough electricity in Indonesia is the long and winding road in securing license to start construction of a power plant. Mr Pamudji complained, some power plants’ license took more than two years to get.

“I asked Mr Jokowi directly to speed up that one-stop service office for business permits,” Mr Pamudji said.

Mr Joko Widodo has delivered his promise to establish a pro-business government, which is able to create a more conducive business climate both for local and foreign investors by introducing the so-called one-stop service office for business permit through the Investment Coordinating Board (BKPM). He acknowledged legal uncertainty and complicated licensing procedures, as well as difficulty in conducting land acquisition, had become major barriers to doing business in the country.

Aside from the land acquisition problem, there are a long list to do for PT PLN to fulfill its obligation in providing electricity in Indonesia, ranging from technical problems to getting more supply from renewable energy.

Java Electrified But Electricity in Indonesia’s Outer Provinces Lags

According to a special report on infrastructure by Standard Chartered Bank in 2011, Indonesia’s electricity market is concentrated in Java, which accounted for around 77.6 per cent of national electricity demand and 78.7 per cent of national electricity production in 2009. Electricity consumption is heavily concentrated around Jakarta, the capital of Indonesia and is the country’s business center.

Among the provinces in Java, West Java and Banten provinces, excluding Tangerang area which are adjacent to Jakarta, have the highest demand for electricity (25.3 per cent of national demand), followed by Jakarta and Tangerang (24.3 per cent).

As Indonesia’s economy and population continue to grow, PT PLN estimates that electricity demand will grow by 9.2 per cent a year on average, almost doubling from 134,581 gigawatt in 2009 to 334,400 gigawatt in 2014.

PT PLN estimates that Indonesia needs to raise electricity production by an average of 3,000 megawatt per year to cope with increasing demand. While Indonesia has a total electricity surplus of roughly 20,000 gigawatt per year, in reality, many areas of the country (including Jakarta) suffer from electricity deficits that lead to blackouts and rationing of electricity supply. Electricity infrastructure development, in particular new power plants, is therefore badly needed to ensure sufficient and steady future electricity supply.

According to data from PT PLN, by the end of December 2012, PT PLN and its subsidiary companies owned and operated about 5,048 generating units with total installed capacity of more than 32,901 megawatt, a 12.41 per cent rise from previous year, of which 25,787 megawatt (78.38 per cent) was installed in the Java island. The total electrification ratio in 2012 reached around 73.37 per cent, which means there are more than 25 per cent of Indonesians without electricity.

The total generating plant capacity broken down by type of power plants are, steam turbine 14,446 megawatt (43.91 per cent), combined cycle 8,814 megawatt (26.79 per cent), diesel 2,599 megawatt (7.90 percent), hydro 3,516 megawatt (10.68 per cent), gas turbine 2,973 megawatt (9.04 per cent), and geothermal 548 megawatt (1.67 per cent).

“Currently we are still struggling to provide electricity to North Sumatra, West Kalimantan and South Sulawesi provinces, as well as outer and several remote islands” Mr Pamudji said, as those areas mentioned continues to experience regular blackouts.

More from 27 November 2014 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/electricity-in-indonesia-needs-not-just-funding-but-land-and-licences-1417021200)
Originally published by The Establishment Post (http://www.establishmentpost.com/many-challenges-providing-electricity-indonesia/)
Print