Electricity Consumption in Morowali and Weda Bay Reaches 15.9 GW, Exceeding Singapore’s
Investment and Downstreaming Minister and Investment Coordinating Board (BKPM) head Rosan Roeslani said electricity demand at the Indonesia Weda Bay Industrial Park (IWIP) and industrial areas in Morowali had exceeded Singapore’s. Singapore’s total electricity consumption currently stands at around 13.1 gigawatts (GW).
Rosan said installed and under-construction electricity capacity at IWIP amounted to 7.1 GW. Combined with 8.8 GW in Morowali’s industrial area, the total reached 15.9 GW.
“This is far greater than Singapore’s total electricity use of 13.1 GW. The energy consumption of these two industrial areas is already greater than Singapore’s,” Rosan said at a launch ceremony broadcast online on Thursday (8 October 2026).
Rosan said Indonesia would become part of the global electric-vehicle battery supply chain by building a complete ecosystem. In Morowali, development would cover the entire EV battery ecosystem, through to battery recycling.
“And in Morowali, these new projects will give us the whole EV battery ecosystem, right through to battery recycling,” Rosan said.
Rosan added that China’s Tsingshan had also contributed to the provision of 2 GW of energy in Sumenep, on Gili Labak and Pagerungan Kecil islands.
“They have also spoken with Danantara about actively participating in the 100 GW solar-panel programme, which we will soon discuss with the Coordinating Minister for Downstreaming,” he said.
Earlier, President Prabowo Subianto inaugurated a downstreaming project at IWIP in North Maluku. It comprises the commercialisation of four industrial projects and the construction of seven new factories at the same site. Together, the projects represent investment of around US$10.2 billion, or Rp180 trillion.
“Today we are launching the first export of electric-vehicle batteries, and then we will launch 11 downstreaming projects, comprising the commercialisation of four industrial projects and the construction of seven new projects at the Indonesia Weda Bay Industrial Park,” Prabowo said at the ceremony, held online on Thursday (8 October 2026).