Editorial: Troubled Road
The Jakarta Post
Bad news for motorists and anyone who regularly passes through the connected streets of Jl. Prof. Dr. Satrio and Jl. Casablanca in South Jakarta and Jl. KH. Mas Mansyur in Central Jakarta, as traffic mayhem resulting from the ongoing construction of a 2.8-kilometer elevated road along the route will continue for some time.
For them, the Jakarta city government’s decision to freeze the construction project in the crowded area is annoying if not outrageous, simply because years of their “sacrifice” for the sake of the infrastructure project will not immediately pay dividends anytime soon, although the work has reached about 90 percent completion.
Once open, the elevated road above Jl. Prof. Dr. Satrio, Jl. Casablanca and Jl. KH. Mas Mansyur will provide motorists traveling between Kampung Melayu in East Jakarta and Tanah Abang in Central Jakarta a congestion-free ride.
The city administration plans to halt the almost-finished project, pending an audit to be conducted by the Supreme Audit Agency (BPK) and the Development Finance Comptroller (BPKP). The elevated road, which is costing the government Rp 900 billion (US$92.65 million), was originally scheduled to begin operating late last year, or two years after former governor Fauzi Bowo inaugurated the project.
“There is something wrong with the project. The contractors have failed to complete it on time although the funds have been disbursed,” Governor Joko Widodo was quoted as saying on Tuesday by Kompas daily.
Deputy Governor Basuki Tjahaja Purnama said the suspension of the project would facilitate the audit and he warned that the city government would not tolerate any officials who may be involved in the alleged misappropriation of Jakarta taxpayers’ money allocated for the project.
The message from the city leaders is clear. Their quest for clean government and good governance will brook no attempt by those entrusted with the infrastructure project to siphon off public funds. Amid the nationwide campaign against corruption, the uncompromising leadership is what we need to stop corrupt and collusive practices, which typify the bureaucracy of the past.
However, considering the fact that the elevated road project is affecting hundreds of thousands of road users, the temporary halt must not last too long. Consequently, the burden will be shifted to the auditors to complete their search for irregularities as quickly as possible, which is neither fair nor effective. The city administration should, therefore, set a deadline that will not compromise the audit’s credibility.
The elevated road will increase the ratio of road area to total area in the capital, which currently stands at 6.2 percent. The government says that with an area of 661 square kilometers and a population of more than 11 million, the city should have a ratio of around 12 percent.
However, the low ratio should not justify massive construction of roads across the city, which is moving perilously close to total gridlock. For better or for worse, public transportation development should remain at the top of the agenda if we want to build a cleaner and safer Jakarta.
Improving public transportation — deploying more buses on Transjakarta corridors, the construction of the mass rapid transit (MRT) system and the monorail — is the only way to significantly ease the traffic. The elevated road project, if and when it is finished, will only put a stop to the grievances felt among one section of Jakarta’s population.