DPRD Demands Completion of Lenangguar-Lunyuk Road Project This Week
The Regional House of Representatives (DPRpend) of West Nusa Tenggara (NTB) Province has summoned the Head of the Department of Public Works, Spatial Planning, Housing, and Settlement Areas (PU Perkim) NTB, along with the contractors of the Lenangguar-Lunyuk long-segment road project, which has exceeded its initial contract period.
During the hearing, members of Commission IV of the NTB DPRD demanded clarity and urged the immediate completion of the Lenangguar-Lunyuk road project to ensure the community can fully benefit from the infrastructure.
The Head of NTB PU Perkim, Lalu Wijaya Kusuma, explained that the project is nearing completion. Of the total project value of Rp 19 billion, only 1.6 per cent of the work remains from the initial contract.
“Only 1.6 per cent is left. We target completion within these 7 days,” said Wijaya following the meeting at the NTB DPRD Building on Wednesday afternoon.
Wijaya detailed several significant field obstacles that caused the delay, including weather conditions, hindered material mobilisation, and equipment breakdowns on the road. Furthermore, extreme geographical conditions presented a major challenge.
“The area is not as easy as imagined. There have been many landslides and road damage from Sekongkang Atas to Lunyuk. The road surface is actually ready for asphalt, but asphalt production was delayed because the contractor had to renegotiate raw material prices,” he explained.
Sabrin, the contractor for the Lenangguar-Lunyuk road project, provided an account of the actual situation on the ground. He noted that the geographical difficulty in the Lunyuk area differs from other regions.
“In Lunyuk, it is different. While we were attempting to complete the work, various landslides occurred, causing road access to be severed,” Sabrin stated.
In addition to natural factors, Sabrin acknowledged technical hurdles that required renegotiations regarding the supply of asphalt raw materials and the operation of the asphalt mixing plant (AMP).
“AMP facilities are very rare in Sumbawa. We had to renegotiate. If the equipment could have returned to normal immediately, the work would have been finished,” he added.
Despite the obstacles, Sabrin reaffirmed his commitment to completing the remaining project without compromising quality. He also stated that the company is prepared to accept financial consequences for the delay.
“We will complete it without reducing technical specifications. The daily fine (one-thousandth of the contract value) will continue to apply, even though the exact calculation is yet to be finalised,” Sabrin asserted.
DPRD Threatens Blacklisting
The Secretary of Commission IV of the NTB DPRD, Hasbdullah Muis Konco, stated that the legislature is seriously noting the expiration of the first contract period for the Rp 19 billion project. In accordance with regulations, the local government is still withholding the remaining budget of Rp 6.8 billion in the regional treasury.
“That money remains intact in the regional treasury and, according to the terms and conditions, cannot be disbursed until the project is 100 per cent complete. The contractor is subject to fines for up to a maximum of 200 days. Once the exact fine is calculated, the remainder will be paid,” said the PAN NTB politician.
Muis emphasised that this case should serve as a lesson for the construction industry in NTB. If a contractor is proven negligent without a tolerable reason, the DPRD urges the relevant department to impose strict sanctions.
“This must be a lesson. We could suggest blacklisting. Otherwise, this will continue to recur and harm the region. We also demand accountability from the Head of Department if this fourth addendum is not resolved immediately, including the work on road shoulders and retaining walls,” he remarked.
Meanwhile, the Vice Chairman of Commission IV of the NTB DPRD, Sudirsah Sujanto, added that the main route of the long-segment project is generally complete and accessible to vehicles. The remaining work is currently focused on road ancillary structures.
“The work is at approximately 98 per cent completion. The road itself is functional and can be used. What remains to be completed are the ancillary structures such as road shoulders, embankments, and retaining walls,” Sudirsah explained.
As the project has not yet undergone the Provisional Hand Over (PHO) and the contractor is still working on-site, Commission IV is committed to monitoring the evaluation and physical work through hearing forums.
“The people of NTB are asking many questions about this long-segment project. We in the DPRD will continue to monitor this seriously and firmly. Our target is that everything must be resolved clearly and cleanly, with the work completed perfectly and the budget payment in accordance with the established regulations,” he concluded.