DIY Regional Government and PLN Strengthen Collaboration to Achieve 100 Per Cent Rural Electrification
PT PLN (Persero) Yogyakarta Distribution Main Unit (UID), in collaboration with the Yogyakarta Special Region’s Department of Public Works, Housing, and Energy and Mineral Resources (PUPESDM), is synchronising the Rural Electricity (Lisdes) programme and plans to complete electricity network construction in several areas of DIY. The meeting took place at the PLN UID Yogyakarta office on Monday (5/10/2026), attended by representatives from the Sleman, Bantul, Gunungkidul, and Kulon Progo regency governments, as well as all UP3 Managers within the PLN UID Yogyakarta environment.
The Head of PUPESDM DIY, Aris Prasena, opened the synchronisation meeting. He welcomed the Lisdes programme and assistance for new electricity connections as part of the government’s efforts to increase public access to electricity.
“In DIY, 100 per cent of sub-districts already have electricity, but we are still working to improve electrical safety and the electrification ratio, which currently stands at 99.9 per cent. The rural electricity programme and assistance for new connections are the government’s endeavours to ensure the community can access electricity entirely,” said Aris.
Aris added that the PUPESDM DIY Department plays a role in synchronising proposals and verifying data from regency/city governments before submitting them to PLN as a basis for programme implementation.
“We are ready to synchronise proposals, locations, and databases that require intervention through the rural electricity programme or new connection assistance. It is hoped that within the next one to two years, these issues can be resolved in DIY,” he said.
During the session, PLN presented the 2026 DIY Lisdes programme, which covers 27 locations across four regencies—namely Bantul, Gunungkidul, Kulon Progo, and Sleman—with a total of 135 potential customers. The programme includes the construction of 0.25 kilometres of medium voltage networks (JTM), 8.67 kilometres of low voltage networks (JTR), and distribution transformers with a capacity of 300 kVA.
As of 5 October 2026, the progress of the Lisdes construction by UID Yogyakarta has reached 70.82 per cent. Based on working areas, the progress for UP3 Yogyakarta and Wonosari has reached 100 per cent, UP3 Sedayu is at 51 per cent, and UP3 Sleman is at 50 per cent.
General Manager of PLN UID Yogyakarta, Deri Prasetio Utomo, stated that synchronisation with local governments is a vital part of ensuring the programme is well-targeted and accelerating construction completion.
“PLN is committed to expanding electricity access for the people in DIY. Through synergy with local governments, we ensure that proposals, potential customer data, locations, and construction readiness are synchronised so that field work can proceed more quickly and accurately,” said Deri.
Through this coordination, PLN and the DIY Government are committed to strengthening synergy in completing the Lisdes programme, including data validation, site readiness, licensing, and local government support, so that more people can enjoy reliable electricity access. This programme also serves as a government effort to ensure equitable development to create social justice for all Indonesian people.
Source: jawawa.id (https://jawawa.id/newsitem/diy-regional-government-and-pln-strengthen-collaboration-to-achieve-100-per-cent-rural-electrification-1791298530)
Originally published by Republika (https://rejogja.republika.co.id/berita/tmhpmu291/pemda-diy-dan-pln-perkuat-kolaborasi-wujudkan-listrik-desa-100-persen), translated from Indonesian