DIY National Road Unit Reports Smooth Trial of 'Kelok 23' Without Accidents
The National Road Implementation Unit (Satker PJN) for the Special Region of Yogyakarta (DIY) has stated that the traffic trial for the Kretek-Girijati section of the Southern Cross Road (JJLS), known as ‘Kelok 23’, proceeded smoothly without any traffic accidents.
The Head of the PJN Unit for the DIY Province, Tisara Sita, stated in Yogyakarta on Tuesday that the trial, conducted from 14 to 20 September 2026, went well and received a positive response from the public. “We appreciate the high level of public enthusiasm for the Kretek–Girijati section. This shows that the existence of this road is highly anticipated,” she said.
According to her, evaluation results showed an increase in vehicle volume during weekends, which led to traffic congestion at several points. However, she continued, no traffic accidents were recorded during the trial period, achieving a ‘zero accident’ status.
“Safety aspects and infrastructure readiness remain the primary considerations before this road is fully opened,” she noted.
Following the conclusion of the trial, the DIY PJN Unit will re-close the Kelok 23 section until the construction of Package Lot 17A at the end of the road is completed. This package includes reducing road gradients, constructing rest areas, and widening the road to four lanes.
She explained that the closure of Kelok 23 will be managed through measured measures using safety equipment such as Mobile Concrete Barriers (MCB), portals, and boundary fences until the road can be fully reopened.
“Further evaluation through joint surveys and the preparation of mitigation strategies for various technical and operational aspects will continue to be conducted,” she said.
She added that the temporary closure does not diminish the benefits of the road section but is a precautionary step to ensure that all aspects of safety, comfort, and traffic flow are guaranteed. “We will conduct a thorough analysis and evaluation to prepare the appropriate operational scheme,” she said.
The DIY PJN Unit will also install additional signage and notices regarding the prohibition of vending and parking on the roadway, install traffic lights (APILL) at the Kretek intersection, and regulate community activities around the road section.
“The installation of signs, prohibitions, and advisories will include both permanent and non-permanent forms,” she said.
Furthermore, the unit will check the condition of drainage and water flow after one rainy season, monitor the cleanliness of the road environment, regulate vendors and parking on the roadside, and educate road users, including prohibitions on stopping or alighting in areas of the road structure not intended for public activity.
“We will conduct a Road Safety Audit (AKJ) following the road’s operation, alongside cross-agency coordination to ensure all safety aspects are met,” she concluded.
Source: jawawa.id (https://jawawa.id/newsitem/diy-national-road-unit-reports-smooth-trial-of-kelok-23-without-accidents-1790060924)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5752481/satker-pjn-diy-sebut-uji-coba-kelok-23-lancar-tanpa-laka-lantas), translated from Indonesian