Diponegoro Street Redevelopment in Singaraja 40% Complete, with Pedestrian Walkways and Drainage in Focus
Redevelopment of Diponegoro Street in Singaraja, Buleleng, Bali, is 40% complete. Work is currently focused on installing andesite stone paving on the pedestrian walkways and improving drainage.
“The project is 40% complete. Andesite paving is being installed in stages, from north to south,” said I Putu Adiptha Eka Putra, head of Buleleng’s Public Works, Spatial Planning, Housing and Settlement Areas Agency (PUPRPerkim), on Friday (23 October 2026).
The area being redeveloped stretches for 258 metres. In addition to the andesite paving, the project includes installing public street lighting and decorative lights, as well as planting trees.
The lights will follow a design similar to those in the Titik Nol Singaraja area and will use solar panels. They will be installed after the main construction work is complete.
Adiptha said the project remained on schedule. Work had previously been held up while large precast concrete sections were installed. Once in place, the sections were excavated and covered again so work could continue.
The redevelopment also includes repairs to the drainage channel. Buleleng’s PUPRPerkim agency has decided to widen it as part of the project.
“The drain is being widened from 80 centimetres to one metre. We have calculated the gradient so that the water flows towards the harbour,” Adiptha said.
Once complete, the redevelopment is expected to make Diponegoro Street in Singaraja more orderly and comfortable for pedestrians, while improving its drainage system.