Depok City Government Explains Delay in Repairing Collapsed Pavement in Sawangan
The pavement on Jalan Raya Sawangan, Depok, West Java, has collapsed and remains unrepaired to this day. The Depok City Government has issued an apology regarding the current condition.
“We apologise for the delay, but we have allocated the budget and a tender winner has been selected; however, we have not yet entered into a contract,” stated the Head of the Public Works and Spatial Planning Department (PUPR), Yodi Joko, in a statement on Thursday (17/09/2026).
Yodi explained the reasons why the pavement has not yet been repaired, noting that the Depok City Government has consulted with the BPKP (Financial and Development Supervisory Agency) regarding the matter.
“On this occasion, I would like to convey that we have consulted with the Inspectorate and the BPKP. We are currently conducting an initial assessment to determine the status of the incident, specifically whether it falls under force majeure or not,” he said.
“That is why we have not yet proceeded with the contract despite having a winner,” he added.
He ensured that once there is progress regarding the tender winner’s contract, the Depok City Government will immediately repair the area.
“We are waiting for developments from the Inspectorate. Following that, we can take actions in accordance with the regulations set out by the contract and other provisions,” he expressed.
He explained that the pavement repair requires consultation with several parties. According to him, once all parties have agreed on the repair, the work will commence immediately.
“After our consultation, the status must first be determined—whether this includes force majeure or otherwise. We will consult with the Inspectorate first, and once they provide their findings, we will follow up,” he said.
It is known that the pavement on Jalan Raya Sawangan, Depok, collapsed despite being only a year old. The Depok City Government has allocated Rp 1 billion to repair the pavement that had recently been put into use.
“This pavement is part of the Kali Cabang Tengah arrangement project, which was carried out in 2023 for the first stage and in February 2025 for the second stage, with a total budget of Rp 9.7 billion,” said the Head of Depok PUPR, Yodi Joko Bintoro, as reported via the Depok City Government website on Tuesday (04/08).
“The repair of the collapsed pavement is scheduled to take place in August 2026, using BTT (Unforeseen Budget) funds of more than Rp 1 billion,” he added.
Yodi explained that the landslide caused retaining wall materials to obstruct the flow of the Kali Cabang Tengah river. Therefore, it needs to be addressed immediately to prevent interference with the drainage function and to avoid wider impacts.
He noted that the landslide site spans approximately 60 metres in length and reaches a height of 3 metres. Currently, the Depok PUPR is completing the administrative stages so that the work can begin as scheduled.
Source: jawawa.id (https://jawawa.id/newsitem/depok-city-government-explains-delay-in-repairing-collapsed-pavement-in-sawangan-1789661975)
Originally published by detikcom (https://news.detik.com/berita/d-8667664/pemkot-depok-ungkap-alasan-trotoar-ambles-di-sawangan-belum-diperbaiki), translated from Indonesian