JAKARTA (JP): The Ministry of Public Works has completed the construction of a 23-km double track railway from Depok to Bogor, West Java.
The Ministry spokesman Bambang Utojo said yesterday the Rp 22 billion project is now being tried out.
The double track system will make the trip between Bogor and Depok safer and faster than the one track system, he said.
It will take less than one hour for the new train to cover Bogor-Depok. The old train took around 90 minutes to cover the route, Bambang said.
The project was carried out by state-owned contractor, PT Adhi Karya. By hiring 120 workers per day the contractor completed the project five months ahead of schedule, he added.
According to the previous schedule, the project would be finished in March 1996, but the company completed it in November this year.
The double track system is equipped with seven bridges and four intersections. (29)